Illinois State Fairgrounds electrical system repairs completed ahead
of schedule and under budget
Send a link to a friend
[April 30, 2008]
SPRINGFIELD -- The state-funded
emergency construction project to repair underground electrical
lines at the Illinois State Fairgrounds is complete and power has
been restored to all areas of the fairgrounds nearly three weeks
before the targeted completion date of May 16. The announcement was
made Tuesday by Jim Riemer Sr., acting executive director of the
Capital Development Board, and Tom Jennings, acting director of the
Illinois Department of Agriculture.
|
"A lot of people went way beyond the call of duty to finish this
project ahead of schedule and within budget," said Riemer. "I'd like
to recognize and thank B & B Electric, the members of Illinois
Brotherhood of Electrical Workers Local 193, HDR Engineering, and
staff from CDB and the Department of Agriculture for making the
timely completion of this vital project a top priority." "This
project certainly has raised awareness about the importance of the
state fairgrounds to Springfield and the surrounding area," Jennings
said. "The fact is the fairgrounds are used for more than just the
Illinois State Fair, and we're extremely pleased -- and more than a
little bit relieved -- to be able to announce that the fairgrounds
are open for business again. I cannot express my thanks enough to
everyone involved in this project for the hard work that enabled us
to finish so far ahead of schedule."
B & B Electric of Springfield began the electrical repair and
replacement work at the fairgrounds March 13. Their bid of $1.86
million was the lowest of five submitted. Workers found collapsed
underground concrete and other undiscovered conditions after the
project began, and this cost an additional $277,000 for necessary
repairs to keep the work on schedule. A total of $578,000 was spent
earlier to identify the cause of the widespread electrical failures
at the fairgrounds, design a solution and make some initial repairs.
The $2.71 million total project cost is considerably less than the
original estimate of $3 million.
[to top of second column] |
The project involved replacing approximately 120,000 feet (22.7
miles) of underground 12,470-volt copper cable that is the main
source of electricity for the entire 366-acre fairgrounds.
The CDB hired HDR Engineering, a nationwide firm with offices in
Springfield, on Jan. 31 to determine the source of electrical
problems that had caused power outages at the fairgrounds and damage
to electrical equipment. HDR's high-voltage system experts
discovered that most of the underground electrical cable was nearing
the end of its recommended service life and was experiencing
insulation failures at numerous locations around the fairgrounds.
They determined that additional, potentially hazardous, electrical
failures along the high-voltage lines were possible and recommended
installing new cable and a new grounding system at the fairgrounds.
[Text from
Capital
Development Board file received from
the
Illinois Office of
Communication and Information]
|