Thursday, February 14, 2008
sponsored by Jake's Furniture

City Discusses Rains, Flooding, Sewers and Services

Send a link to a friend

[February 14, 2008]  Severe weather that's made headlines off and on for more than a month has caused a lot of headaches. Heavy rains, thawing and heavy snow washed away by more heavy rain have overwhelmed the city storm sewer system a couple of times over. The excessive water took has taken its toll on the city's citizens, storm sewer system and roadways.

Many residents found themselves bailing flooded basements at the end of the first week of January. Inherently a wet and cold task, it was particularly unpleasant as a mid-winter event.

Wastewater treatment plant manager Dave Kitzmiller explained the cause. Six of the 11 lift stations that aid in getting wastewater to the sewer plant in Lincoln were overwhelmed. It took two days before all six lift stations caught up.

Kitzmiller said that 20 basements were reported flooded by storm sewer backups.

He said that the wastewater treatment plant normally processes 3 1/2 million gallons a day. During this event it jumped to over 7 million gallons a day for several days.

Just over a week ago, on Feb. 4, another heavy rain fell, and that rain fell over the 10.5-inch snow that had blanketed the area just four days earlier.

The result was similar to the 5-inch rain we had last month, Kitzmiller said. The good news, he added: "I did not get any basement backup calls."

Melting snow and ice flooded streets and streams. But, the storm sewers were not as affected this time, he said.

Again, six lift stations could not keep up. Five of the stations returned to non-emergency levels by Feb. 6.

The south lift station, located on Salt Creek, flooded up around the bypass, and the station was pumping creek water as well as sewer for a time, Kitzmiller said. All stations are now returned to normal.

The collapse of a storm sewer on Route 121 as you head south, near Precision Products, had nothing to do with the recent weather. It was found that a water line that was drilled through the storm sewer years ago had leaked, slowly causing the deterioration. The water company is taking responsibility for it.

[to top of second column]

Petersburg Plumbing has been assisting with the assessment of the needs and costs for those repairs. Because it is an urgent situation it will not be bid out.

Also, because it is on a state route, the state has the permitting process on the fast track. The work could get done as early as next week, Kitzmiller said.

Two other roads have issues. Barricades are up on 21st Street. The water flow has been too high to scope it to see if it is a sewer or street problem, Kitzmiller said.

More barricades are up at 15th Street, where it is a sewer problem that has been identified.

Kitzmiller said during a break from the meeting that there is a big presentation planned later this year that explains a lot about how the whole system works. The information that would be presented would benefit the public to know.

It was mentioned that Aldermen Marty Neitzel and Kathy Horn were part of a group that recently toured the wastewater treatment plant.

Neitzel said, "I wanted to see how it goes from this point to that point. I was impressed with the process."

Alderman Buzz Busby said he's toured the place many times before. "I can understand why you were impressed. The first time I saw it, I was (impressed) with the cleanliness of it."

Neitzel chimed back, "Above all."

Busby, "Right! And it wasn't done just for your visit either."

Horn cheerfully added, "I've never seen someplace run by so many men be so clean and organized."

"I think I take that as a compliment," Busby laughed.

[By JAN YOUNGQUIST]

< Top Stories index

Back to top


 

News | Sports | Business | Rural Review | Teaching and Learning | Home and Family | Tourism | Obituaries

Community | Perspectives | Law and Courts | Leisure Time | Spiritual Life | Health and Fitness | Teen Scene
Calendar | Letters to the Editor