Illinois State Fairgrounds Closed Through Late May
Electrical Failures Lead to 22.7 Miles of Cable Replacement
Send a link to a friend
[February 28, 2008]
SPRINGFIELD -- Capital
Development Board Construction Administrator Ron Wright and Illinois
Department of Agriculture Director Chuck Hartke announced Wednesday
that a state-funded emergency construction project is under way to
repair the recently discovered, widespread high-voltage electric
system failures caused by deteriorating, more than 25-year-old
underground lines at the Illinois State Fairgrounds. The fairgrounds
will be closed to all activity through late May to allow crews to
replace 120,000 feet of high-voltage cable as quickly as possible
without exposing people to potentially hazardous situations.
|
"The Illinois State Fairgrounds is a very important state resource.
And, making sure the facilities are safe for everyone who depends on
them is our top priority," said Wright. "Most of the electric cable
underneath the fairgrounds is more than 25 years old, and unless it
is replaced we will continue to experience failures. This monumental
project is also a prime example of why lawmakers need to approve a
capital construction bill. Governor Blagojevich has called for a
capital bill for five years that would address the state's
infrastructure needs, and this is another example of why we can't
wait any longer." "I commend the Capital Development Board for
their prompt attention to this matter," Hartke said. "The
fairgrounds are utilized throughout the year, not just during the 10
days of the Illinois State Fair, and this project will ensure they
remain a center of activity and a popular community gathering
place."
Bids for the estimated $3 million project will be opened on March
12, with work to begin immediately following the contract award. The
project will involve replacing approximately 120,000 feet (22.7
miles) of underground 12,470-volt copper cable that is the main
source of electricity for the entire 366-acre fairgrounds. The
electrical work at the state fairgrounds will be paid for by
re-prioritizing a limited amount of funds available for work at
state facilities.
[to top of second column]
|
The Capital Development Board hired HDR Engineering, a nationwide
firm with offices in Springfield, on Jan. 31 to determine the source
of electrical problems at the fairgrounds. A cable fault on Jan. 25
caused a power outage to a portion of the grounds. Then, on Jan. 28,
a single pad-mounted switching cabinet was damaged by another cable
fault, and on Feb. 15 a manhole cover was blown from its opening,
also due to a cable fault. Power was shut off to the majority of the
fairgrounds following these incidents so HDR's experts in
high-voltage systems could safely test nearly 24,000 feet of
underground cable. HDR discovered that most of the cable was nearing
the end of its recommended service life and was experiencing
insulation failures at numerous locations around the fairgrounds.
They determined that additional, potentially hazardous electrical
failures along the 12,470-volt lines were possible.
The successful bidder for the project will install new
high-voltage underground cable and a new grounding system at the
fairgrounds and replace the damaged switching cabinet. Working in
sections, crews will pull the old cable from its concrete-encased
conduit system, use a special camera to check conduit integrity and
clean the interior of the conduit before pulling in new cables.
All of the public events scheduled through late May at the
fairgrounds have been relocated, rescheduled or canceled. The
Department of Agriculture, Department of Natural Resources and
University of Illinois Cooperative Extension Service offices remain
open since they are on separate electrical circuits. For a list of
previously scheduled fairgrounds events and their status, visit
www.agr.state.il.us or
call 217-782-1698.
[Text from
Capital
Development Board file received from
the
Illinois Office of
Communication and Information]
|