Update for City of Lincoln road work

Send a link to a friend  Share

[June 07, 2014]  LINCOLN - The priming and seal coat project is running 3 days behind due to the weather early in the week and it will continue the week of June 9, 2014.

The Heater Scarification project will begin June 17, 2014 and go through June 24, 2014 in the following areas:

  • Oakhill Dr. from Memorial Park Rd. to the west.
     
  • Broadwell Dr. from Lincoln Parkway to South State St.
     
  • North Union St. from 11th St to Keokuk St. /Woodlawn Rd.
     
  • Railsplliter Ave. from Airport Rd. to Lincolnwood Dr.
     
  • Heritage Ave.
     
  • Clinton St. from South Logan St. to South Chicago St. and from South Sangamon to Immanuel Lutheran Church parking lot.
     
  • Wyatt Ave from South Kickapoo St. to South Sherman St.

[to top of second column]

After the Heater Scarification is completed and starting June 23, 2014 contractors will begin the Micro-surfacing on the same streets. Streets will not be closed completely but there could be short delays and temporary limited access.

With Rain in the forecast for next week there could be further delays.

[Text received; WALT LANDERS, CITY OF LINCOLN STREET SUPERINTENDENT]