Logan County Board
September Road and Bridge

Send a link to a friend  Share

[November 04, 2015]  LINCOLN - Road and Bridge Meeting, Blue Room, Logan County Safety Complex August 31, 2015

Present: Rick Aylesworth; David Blankenship; Gene Rohlfs; Chuck Ruben; Scott Schaffenacker Absent: Bob Farmer
Guests: Bret Aukamp; Curt Fox

Mr. Blankenship called the meeting to order at 7:32 pm.

A motion was made by Mr. Schaffenacker, seconded by Mr. Aylesworth, to approve the minutes from the August 3, 2015 meeting. Motion passed.

The list of claims for payments was reviewed. A motion was made by Mr. Aylesworth, seconded by Mr. Schaffenacker, to approve the list of claims for payment. Motion passed.

Monthly report on current maintenance and construction:

Maintenance Report: The County’s sealcoat program had good progress is August. It is in the final few weeks of work. There are still 2 townships, 2 villages, and several miles of County Highways to complete. There were several locations on County Highways where the road base needed repaired. All those sections have now been seal coated. A second coat will be applied in the next few weeks, which should be enough to waterproof the roadway before winter. The crew has been patching various locations around the county, mainly on CH 12 west of Broadwell and CH 14 north of New Holland. Several field entrance culverts that were requested last winter have been finished. The department is not able to be very timely with culvert requests; Mr. Aukamp tries to consolidate the backhoe projects in the respective areas of the County, completing as many as possible while the equipment is in the area. For that reason, there are times when customers have to wait. The department’s college interns are back to school, so the crew is back to 6 men. This is a busy time of year as the sealcoating program and all summer projects are in full swing.

Construction Report: The Orvil township bridge project on 2200th Street is underway. The old bridge has been removed. The piling has been driven for the new bridge, and one of the abutments has been poured. The department is on schedule to set beams on this bridge sometime right after Labor Day. It is scheduled as a 35 working day project. It is currently in week 2.
 


Engineering Report: The State of IL recently awarded the joint purchasing contract for rock salt. Logan County did get a contract this year. The awarded bid price is $63.96 per ton. This is 38% less than last year, and comparable to what has been paid in the past. MFT Status: The department is not currently receiving any Motor Fuel Tax revenue. It’s not a huge issue for Logan County right now because there are balances to fall back on to continue operating. There is an issue with several of the bridges along the Lake Fork ditch. The drainage district has been dredging the ditch and piling the material along the channel levees, raising the elevation by several feet. Until now, this problem has only affected township bridges, and Mr. Aukamp doesn’t believe that they have approached the drainage district about the problem. Recent dredging at the County Highway 1 bridge south of Mt. Pulaski has caused the channel levees to be raised above the low- beam elevation of the bridge. During flood events, the water is now contained in the channel and put lateral pressure on the bridge beams. Mr. Aukamp will contact the drainage district to discuss the problem.

Old Business:

1) High Speed Rail Crossings:
The rail crossing at Broadwell is expected to be closed for replacement in the near future. There is concern about when it will begin or how long it will take. The latest set of plans showed roadway work on both sides of the crossing. The crossing will include a second set of tracks since Union Pacific has extended their rail siding through this area. Mr. Aukamp has a meeting scheduled this week to discuss construction plans in Lawndale. The current design plans show the Main Street crossing to be closed, with roadway improvements to be made at the Lincoln Street crossing and other improvements. Cost estimates to validate the need for the improvements will be reviewed.

[to top of second column]

2) Improvements to CH 3 (San Jose Road) and CH 16 (Delavan Road): This project began last week and is nearly complete. IRC had their road recycler grind both roadways on Monday and Tuesday. Oil was applied on Thursday and then mixed with the loose aggregate. A grader and vibratory roller have been working the roadway for several days to help establish a proper crown, and to provide adequate compaction. The road needs some time to cure, while the water evaporates from the emulsified oil. The plan is to sealcoat these roads in a few weeks. Cost-per-mile numbers are not ready yet. Mr. Aukamp’s rough guess: 100,000 mile but had originally budgeted 200,000 miles.

3) Repairs to County Highway 6 (Atlanta-Beason): This project is mostly complete. About 4 inches of additional rock was added to the roadway to help strengthen this section. The department’s grader was used to establish a uniform crown but rented a vibratory roller to provide some compaction. The grader was used to pull dirt from the ditches toward the shoulders. There are smooth foreslopes over the project, but there will be a need to add dirt along the shoulders in several places.

4) Road Conditions and Funding: Nothing to report.
 


5) Equipment Purchases: The State of IL recently awarded the join purchasing contract for dump trucks. Mr. Aukamp is working with Rush Trucking to get an order form and vehicle specifications, but is still waiting. The goal is to purchase one quickly, before the first snowfall. Due to only having $60,000 in the current year’s budget for equipment purchase, Mr. Aukamp may need to request a budget amendment this month. The State bid price is $123,000 and it may still need a plow and/or salt spreader.

New Business:

1) Resolution to approve a County Aid request for funding from the County Bridge Fund to replace a culvert on 1500th Street in East Lincoln and Chester Twps. (Section 115-B-CA) The County’s share would be as much as $25,000. A motion was made by Mr. Aylesworth, seconded by Mr. Rohfls to bring the resolution forward to the full Board. Motion passed.

2) Resolution to approve a County Aid request for funding from the County Bridge Fund to place riprap under a bridge on 2300th St in Atlanta Twp. (Section 215-B-CA) The County’s share would be as much as $10,000. A motion was made by Mr. Ruben, seconded by Mr. Schaffenacker to bring the resolution forward to the full Board. Motion passed.

3) Engineering Services Agreement with Cummins Engineering for design work on a bridge replacement project for Prairie Creek Twp on 2300th St. (Section 15-15128-00-BR) The not-to-exceed cost is $29,900. The County’s share would be 10%. A motion was made by Mr. Ruben, seconded by Mr. Aylesworth to approve the agreement. Roll Call vote taken, 5 yes 0 no. Unanimously passed.



4) Wind Farm Road Use Agreement: Nothing to report.

5) Quarterly project status report: Mr. Aukamp will provide this information next month for each member.

A motion was made by Mr. Aylesworth seconded by Mr. Rohlfs, to adjourn the meeting. Motion passed. Meeting ended at 8:23 p.m.

[Copied from Logan County website]

Back to top