Farnsworth Group discusses errors
made at new Lincoln Street Department Facility
Picks up the cost for correcting many of
the problems
Send a link to a friend
[May 15, 2017]
LINCOLN
- After the Tuesday night meeting of the Lincoln City Council last
week, Don Adams of Farnsworth Group summed up an earlier
presentation he made saying, “It’s complicated, but the bottom line
is we made a mistake.” He would go on to say that Farnworth was
taking responsibility for their error, and would make it right
financially.
The presentation began with John Bishop introducing Adams who then
explained a request before the city council for change orders
relating to the City Street Department’s new facility on Limit
Street.
Adams said this was not the kind of presentation he enjoyed giving,
but in the interest of being transparent and straight forward with
the city, he was there to tell them that Farnsworth Group had made a
costly error in laying out the storm water drainage plans for the
new facility.
He said that when the site plans were being developed, there was a
manhole on the property that should have been inspected and traced
to see where it led. That work was not done. The result was that the
Farnsworth engineers and designers had mapped out the storm water
drainage that included underground storm sewer lines, unaware there
was a sewer line in the pathway.
Adams said that was the first mistake. When construction began on
the underground pipes, they ran right into the sewer line. Adams
summed it up to the council saying, “It was our stupid mistake,”
Therefore, he said, the construction was halted and an alternate
plan was drawn up.
However, Adams said that though the manhole had been noted and the
sewer line marked, what they didn’t find out was that a few feet
from the manhole, the sewer line made an abrupt turn, resulting in,
once again, the storm water drainage pipe intersecting with the
sewerage lines.

In the end, Adams said that the storm drainage was redesigned again,
and a new special structure called a “conflict structure” was added
to the plan. Adams said the underground lines are going to be close
together, and building this type of structure would provide easier
access to all the pipes as opposed to manholes that are typically
used.
Adams said that Farnsworth was taking full responsibility for the
errors made, and would be paying the large portion of the additional
costs involved. He said that looking at the situation now that they
have all the information, Farnsworth engineers would have added a
conflict structure to the plan early on had they realized they were
dealing with the underground sewer.
Taking that into consideration, Farnsworth is going to pay all the
additional costs except the cost of the conflict structure.
Adams said there were two additional oversights that are addressed
in change order number five.
[to top of second column] |

Farnsworth had not taken into consideration the land swap
agreements with Illinois American Water. Therefore, the security fencing around
the facility had been put in the wrong spot. Adams said the fencing had to be
moved and Farnsworth had taken on the entire cost of that work.
Also, Ameren Illinois needed access on one side of the property,
and the fencing interfered with that access. Therefore a gate had to be added
specifically for Ameren. Farnsworth was also going to take care of the added
cost for that adjustment.

After his presentation, Adams was asked by Steve Parrott if the Farnsworth Group
had made these kinds of mistakes on other projects. Adams said absolutely not.
He went on to say that the errors made with the street department design had
been the topic of much discussion within the firm. He said that there had been
adjustments made to design procedures that will help assure that errors such as
this are less likely in the future.
Rick Hoefle commented that he appreciated the Farnsworth Group
coming to the full council to explain the situation. He said it was the kind of
open, transparent communication he expected from the group.
At the voting session of the Lincoln City Council tonight aldermen will be asked
to vote on the following motion:
“Approval of change order with the Farnsworth Group for the new street garage in
an amount not to exceed $65,349.50, with certain costs to be reimbursed by the
Farnsworth Group in an amount of $26,151.”
The city will then be responsible for an amount not to exceed $28,198.50.
However, this will be a pass-thru expense for the city because the cost of
building the new facility falls on Common Wealth Edison and Nicor Gas as a part
of the Environmental Protection Agency orders for remediation at the old
facility on Third Street.
On a positive note, the construction of new Street Department is reported to be
98 percent complete. The main building will house the street department offices
as well as staff areas and equipment storage, plus new offices for the Building
and Safety Department.
[Nila Smith]
 |