Board discusses options for Logan
County’s jail and courthouse
Send a link to a friend
[October 16, 2018]
LINCOLN
At the Logan County Board Workshop on Thursday, October 11, there
was some discussion on the upcoming referendum for the public safety
tax that would help with courthouse dome repairs and jail expansion.
The previous referendum for the public safety tax failed last
spring, but it will be on the ballot again this spring.
Sheriff Steve Nichols talked to the board about the courthouse and
plans for the referendum this spring.
Nichols said he spoke with the sheriff from Crawford County. There
they had an assessment that gave two options. In Crawford County,
option one was for a new 12,000 square foot building, demolition of
the old building, and site development at an estimated cost of $5.5
million to $6.3 M. Option two was adding 16 more beds, doing
renovations, demolition, and site development at a cost of $4.6 M to
$5.4 M.
Nichols said for the jail here, the only option that has been
discussed is expanding the jail and renovating certain parts of it.
Nichols said there is space not being utilized in the courthouse
because of the building itself.
Nichols showed board members recent photos of the inside of the
courthouse He has had the rotunda roped off again due to chips
coming down because the plexiglass has not slowed that down. Nichols
said in addition, the third-floor courtroom “leaked like a sieve
last week during all the rain.”
Nichols said he has talked to people and told them the referendum is
for the courthouse and the jail. He said, “They are all in on the
jail, but they are not all in on the courthouse.”
Nichols said, “I think you better take a hard look at this and
decide which way you want to go. He said spending $4 M on a dome
that is just going to continue to give us problems in an old
building does not seem like good use of $4 M when that will probably
take you 33 percent of the way to a new jail and courthouse.
Nichols said they are “fighting an uphill battle” and if both are on
the referendum, neither one is likely to pass.
Chief Deputy Mark Landers said they asked the architects that are
doing a basic feasibility study for the jail what it would take to
get option two on the table. He said it would be another $25,000 for
engineers to look at expansion, who would have to talk to the
county’s judges, clerks, and state’s attorney to see what is
possible and whether the land we have is sufficient to make that
happen.
Landers said he thinks the public should be given two options asking
whether they want to repair the dome and do a jail expansion or
whether to do a new complex at the jail.
Nichols said a new facility would hold 70 to 80 inmates. The jail we
have now holds 65 inmates.
Board Chairman Chuck Ruben said he knows a study is needed for
decision making purposes. He said Effingham had built a Law and
Justice Center a few years and he asked Nichols to contact them
about that cost.
Ruben said if costs are reasonable, maybe the county could afford to
do that.
Board member Dave Blankenship supported giving the public an option,
he would still suggest a feasibility study regarding the tiering off
of the expenses of the other facility, so the public has got a good
idea of the plans. He said that way, they are not just looking at
the dollars and cents to build, [but] they are looking at how much
revenue we would decrease in expenditures by not trying to maintain
so many facilities.
Blankenship said there are all sorts of feasibility studies and they
would not have to do an excessive one, but could do a basic study to
figure out what they are going to save in insurance and on
utilities. He said it might be something to consider incorporating
when presenting the information to the public to see how they feel.
Board member Scott Schaffenacker asked Nichols if he would like two
separate referendums.
Nichols said, yes, because it could help them pass.
Board member Kevin Bateman said there is not enough maintenance
staff to maintain the Courthouse and when he suggests work to be
done, it gets overwhelmed by other work orders. Bateman said he
would get more involved if needed by fixing the leak on the third
floor.
[to top of second column] |
Bateman said it is on an old building, but they have had studies done showing
the bones of the Courthouse are still strong and the dome suffers from lack of
maintenance.
Nichols said he agreed with Blankenship that doing a study on utilities and
water usage and everything else is going to be as important. He said if we are
going to the public and asking them to spend money, they deserve to have all the
numbers.
Nichols said it is better than pouring $4 M into a dome that is an “eyesore”
needing continuous repairs, when the whole building needs repairs. There is
excess space that is not being used and maybe in a different building, they’d
utilize the space more efficiently. He said maybe the dome could be removed and
a new roof could be put on.
Ruben said he wants a generic building architectural plan put on the board
agenda for Tuesday and then if we determine from what is brought forward that we
want to spend the $25,000 [for a feasibility study], we could go ahead and do
it.
Ruben said we are going to have to get rolling because it is going to jump up on
us quicker than we think.
Bateman said if we are spending the extra money for a feasibility study, we have
to include the cost of removing the dome and making the building weather tight.
Fixing the leak must be part of any options.
Blankenship said it seems a little premature to only discuss two options in this
forum when you only have a few minutes to discuss it. He said there are probably
other options available and more time is needed to explore that.
Bateman said fixing the leak must be part of any option.
Ruben said under constraints of what the board is trying to pass, we have $10 M,
so if we see that a new Law and Justice Center would cost $15 M, we either have
to figure out another thing to put on the ballot to raise more money or we would
have to go with a lesser plan to fit the dollars we have available to spend.
Ruben said we can go forward with this fairly quickly because if we get rough
figures, it may be a “moot” point to even consider these other options if it is
going to over expend the amount of money available.
Board member Gene Rohlfs asked what the $4 M to be spent on the dome would
include.
Bateman said it would cover the removal the entire exterior structure, putting a
new copper dome on it with a 100-year warranty, fixing the interior dome, and
putting a glass structure in and plexiglass structure over that so the
stained-glass portion would always stay.
Rohlfs said it sounds like if that would be done, then the maintenance on the
dome after that would be minimal.
Board member Bob Sanders said we need to weigh all options. Many counties have a
jail in the courthouse for security purposes. He said utilities would likely be
less than what they are now.
Blankenship said energy efficiency audits have shown it is hard to keep up with
the preventative maintenance that will keep the mechanicals and HVAC on all the
buildings.
Blankenship said he is not in favor of tearing the Courthouse down, but he wants
to know what constituents say about it. He thinks we should find an option to
retain this facility that is beautiful, cohesive with downtown Lincoln, and good
for tourism.
Blankenship said looking at raw dollars and cents and what he sees looking at
these buildings in his profession, then we have got serious problems. If we look
at the other way and the public is willing to go along with it and spend extra
money, that would be good wisdom because we are going to gain efficiency.
Bateman said a recent energy audit showed the courthouse is one of the most
energy efficient buildings. He said putting $40,000 to $50,000 in the budget to
hire someone who just does building maintenance would help.
Blankenship said business continuity would be easier to maintain in one facility
than in multiple facilities.
The board will consider options after they hear more about architectural plans.
[Angela Reiners]
|