Logan County Board grants Sugar
Creek Wind Farm staged construction
Send a link to a friend
[March 21, 2019]
LINCOLN
On Tuesday, March 19, the Logan County Board held its monthly voting
meeting. One focus of discussion was about changes to the upcoming
Sugar Creek Wind Farm Project.
Members present were Board Chairman Emily Davenport, Vice chairman
Scott Schaffenacker, Kevin Bateman, Dave Blankenship, Janet Estill,
Bob Farmer, David Hepler, Steve Jenness, Chuck Ruben, Bob Sanders,
Annette Welch and newly appointed board member Jim Wessbecher.
Planning and Zoning Committee Chairman David Hepler brought forward
three motions related to work on the Sugar Creek Wind Farm Project.
The first measure was to modify conditions two, three and four that
would allow phased construction for the Sugar Creek Wind Farm.
Initially, condition three required that tower foundation
certifications be required prior to the issuance of a turbine
foundation building permits.
Conditions two, three and four are all related to the tower design
and turbine, and required prior to the issuance of turbine
construction permits.
The second motion was to allow nighttime construction activities
unless prohibited by the Road Use Agreement for Sugar Creek Wind
Farm.
The third motion was to use Patrick Engineering for Engineering
Consulting for the Sugar Creek Wind Farm Decommissioning Plan.
Bateman said he wanted to amend the first motion to allow all
construction except what is prohibited by the road use agreement,
but Ruben said the motion to allow nighttime construction activities
unless prohibited by the road use agreement already covered that.
Blankenship said he wanted to amend the first motion to add in
wording about a pre-operational phase on the decommissioning
agreement. Blankenship wants the decommissioning agreement to begin
before construction, so that if they fail to proceed with work after
the foundation is set, the company would be still be responsible for
decommissioning.
Schaffenacker said he felt that was covered in the third motion
regarding the decommissioning plan. Ruben said wording could be
added to the third motion saying the plan would apply from the
beginning of construction.
Hepler asked if that would be problematic.
Kyle Barry, the attorney representing the project, said it depends
on how it would be implemented. The decommissioning plan is prepared
by consultants who direct Patrick Engineering to consider what is
appropriate to cover.
Hepler said the county is hiring Patrick Engineering because they
are experts and he feels more comfortable letting experts come back
with their recommendation for the board. Otherwise, Hepler said it
seems like the board is telling Patrick Engineering how to do their
job.
Bateman said he agreed with Blankenship about the Decommissioning
Plan having a provision in it about the pre-operational phase. If
the company pours four tower foundations and then something happens
and they do not build the wind farm, Bateman said the farmer would
have four holes sixty feet deep with concrete rebar. Bateman said
there should be a statement is needed that once they start
construction, there should be a decommissioning plan.
Ruben said he is not questioning the expertise of Patrick
Engineering, but at what point the decommissioning plan is
beginning. Patrick Engineering’s expertise is in how many yards of
concrete have to be taken out, how much the steel is worth, how much
will be recovered in scrap and how much decommissioning is going to
cost.
[to top of second column] |
Ruben said it is the board’s job to see the plan applies across the board. He
said if the concrete for the [turbine] bases is poured, the company will build
the towers. It would take some calamity for them not to build the wind farm
since a lot of money has already been put into the project. Ruben agreed that
having something in the plan to protect against the work not being done might be
good.
Ruben said he would amend the motion for the Decommissioning Plan to go into
effect at the beginning of construction.
Before any voting was done, Logan County Highway Engineer Bret Aukamp said Sugar
Creek is asking to proceed with the construction schedule.
Aukamp said there is a “big ask” for Fifth Street Road and hopes that is
considered when the road use agreement is negotiated.
The board then voted on the first motion as it was originally written. Phased
construction for Sugar Creek Wind Farm was unanimously approved.
Hepler’s motion to allow nighttime construction activities unless prohibited by
the road use agreement with Sugar Creek was amended by Ruben.
Ruben said the board had thought there were certain items covered by the road
use agreement that are not covered. In the amendment Ruben said he wanted to
insert that nighttime construction activities should be allowed “on the wind
towers and in the field, not up and down the road [and] not delivery to the lay
down yard.”
Bateman wanted to add ‘in access roads.’
Ruben said tower construction and maintenance on the vehicles at night should be
allowed as they are minor.
Schaffenacker asked if access roads and fields are part of the road use
agreement.
Aukamp said access roads and fields are on private properties, so they are not
covered in the road use agreement. Typically, that type of construction and work
on these roads is done during the day, he said.
Barry said he did not have any problems with these amendments.
The amendment and main motion were both unanimously approved.
Hepler’s motion to approve Patrick Engineering for engineering consulting for
the Sugar Creek Wind Farm Decommissioning Plan was also amended by Ruben.
Ruben’s amendment was to add that the decommissioning plan would go into effect
at the beginning of the concrete tower pours.
Bateman asked about changing it to the beginning of construction and Ruben
agreed with that change.
The board approved the amendment with 10 yeses.
Hepler voted no.
Schaffenacker abstained.
The board approved the main motion for Patrick Engineering to provide
engineering consulting for the decommissioning plan with 11 yeses.
Schaffenacker abstained.
[Angela Reiners]
|