Logan County Courthouse
restoration includes elevator, HVAC and technology systems, and
input of office holders
Send a link to a friend
[May 27, 2020]
At the special board meeting Thursday, April 30, Building and
Grounds Committee Chairman David Blankenship gave some updates on
the progress toward the courthouse restoration.
Though the dome is still a top priority, Blankenship said there are
other areas that need to be addressed soon.
One issue is the inside elevator that five years ago had extensive
work done at a cost of $144,572.79.
Blankenship said in 2015, Kone replaced the controller, door
operator, hall and car buttons, the cab interior, the governor, the
governor’s ropes, the rope gripper, the motor and the wiring. The
traction machine, elevator car sling and platforms, rails,
counterweights and counterweight ropes were all reused.
Since then, Blankenship said there has been eleven service calls
with repairs costing a total of $14,155.58. In addition, the county
has spent $111.17 per month for a lube and inspection contract.
Currently, the county is attempting to acquire an obsolete sheave
pulley that if secured will require all new elevator ropes/cables.
The sheave pulley, cables and exhaustive labor are estimated to cost
anywhere between $35,000 and $60,000. If custom manufacturing is not
available, the elevator machine will have to be replaced and that
cost would be somewhere between $80,000 and $100,000.
Both Blankenship and Walter are looking into the availability of
parts and various options to resolve the reliability issues.
Regardless of the action taken, the county is facing extended
downtime. It would take four to eight weeks to get the pulley and 12
to 14 weeks for a whole new machine.
Blankenship, Walter and a Kone elevator representative met to plan a
course of action.
Blankenship said the persistent elevator problems and continued lack
of mechanical system reliability represent unnecessary financial
drains on the county budget.

Other updates:
Some public officials have expressed concerns with the current
condition of boiler and the potential of a catastrophic winter 2021
breakdown. Blankenship was asked about retrofitting a new boiler
prior to winter 2021. He strongly advised the board to not take that
approach due to the necessity of matching the new boiler to the
current heat distribution system (piping/registers etc…).
Numerous pipes are leaking. Blankenship said there are a myriad of
other problems, so the current heat distribution is not efficient.
Blankenship said the optimum approach would be a placement of a
mechanical room on each level of the courthouse. This approach would
allow for a dedicated zone controlled heating and cooling system on
each level.
The system would be designed and engineered with computer logic
control that would respond if a single heating system fails by
calling upon another system to compensate for the loss until repairs
can be made.
Such a system will provide maximum energy efficiency as well as
continuity of government should a breakdown occur.
Blankenship said a single large non-modulating system would likely
limit or not qualify for current energy rebates nor would it provide
redundancy in the event of a breakdown.
If the current boiler system has a catastrophic failure, Blankenship
said construction conditioning trailers would be brought in to
condition the courthouse. This would be far better than undertaking
a residential R & R (Remove & Replace) approach of the existing
system.
Walter is working on an energy audit to determine the best equipment
design. He does not want money to be wasted not knowing if the
boiler system may be obsolete months down the road. Walter said the
system must be compatible with the restoration and the replacement
of the existing boiler would not be.
[to top of second column] |

Courtroom
Another priority is the third-floor courtroom. This is where the ceiling tiles
fell in last May due to leaks from the dome. Walter had been considering what
will be required on a modest scale to get the courtroom back in a position to
conduct business, which would be limited to clean up and stabilization.
After looking further into the costs for the third-floor repairs, Blankenship
found they were prohibitive. With the approval of Judge Jonathan Wright, the
county will continue using the Orr Building across the street for courtroom
space.
With the need for additional courtroom space, the county had already been
leasing the Orr Building across the street from the courthouse for several
months. The contract is up in June. Blankenship talked to State’s Attorney Brad
Hauge, Judge Jonathan Wright, and Bill Walter about keeping the Orr Building
lease as work continues.

On Tuesday, May 19, the board unanimously approved renewing the Orr building
lease for six months.
During renovation, Blankenship said there may be additional indirect expenses
unrelated to construction due to leasing, storage and rental, etc...
Blankenship recently forwarded a letter to Walter advising him that the
Courthouse referendum passed on March 17, 2020. It also authorized him to
proceed with compiling bid specifications and documents.
In a recent phone conversation with Chairman Emily Davenport and David
Blankenship, Walter indicated he already has numerous specifications completed.
Blankenship and Walter will soon be meeting with contractors to discuss project
goals.
Walter requested that Blankenship appoint a Technical Restoration Committee of
skilled technical individuals. This group would be “think tank” committee
working with Blankenship and Walter and be charged with the purpose of
developing technical recommendations. These recommendations would be submitted
to the Buildings and Grounds Committee. If approved, they would be submitted to
the entire board for a binding decision.
In addition to the tech committee, Walter has requested the full board appoint a
Restoration Transition Committee comprised of both public officials and county
employees. Their purpose would be critical to coordinate and execute all
in-house efforts required to keep the county government functioning during the
restoration process. These efforts may include equipment and staff relocations,
storage, IT needs during construction and scheduling coordination with all
pertinent parties. This committee would make recommendations and coordinate
their efforts with Walter, the Buildings and Grounds Committee and the County
Board.
The dedicated committee approach requested by Walter will form a working team
with each functioning within their respective disciplines.
Blankenship said this type of structure is required on a project of this
magnitude as it forms a proper chain of command as well as keeping the public
informed. It also provides a medium of input for public officials.
At the Regular Board meeting in May, the board approved the formation of both
the Technical Restoration Committee and the Restoration Transition Committee.
In the later stages of restoration, Walter said a décor committee made up of
both the public and private sector should be formed This committee would be
limited to giving aesthetic recommendations to the board regarding topics such
as colors and flooring.
To keep on schedule with the bond company, board member Chuck Ruben reminded
Blankenship at the special meeting that David Pistorius needed physical
documentation. At a subsequent meeting, Blankenship confirmed that those
documents had been submitted.
[Angela Reiners] |