Logan County Courthouse dome structural preparations to do restoration near completion

Send a link to a friend  Share

[June 05, 2021] 

In the past several weeks, the American Scaffolding Company has been erecting the scaffolding around the Logan County Courthouse dome.

The scaffolding now surrounds the dome on all sides and is supported by I Beams.

 



An interesting view of the scaffolding and I Beams from Latham Park makes the dome look almost like a spaceship preparing for take-off.

Close-up views of the dome show the deterioration and paint that has flaked off over the years.

[to top of second column]

 

With the scaffolding up, the next step will be to encapsulate the dome with plastic before the dome restoration begins.

Next week, project manager Bill Walter of MRTS will be reviewing the dome specifications with the Construction Technical Committee. He will soon do an initial review of the construction management portion of the restoration project with the Logan County Board Building and Grounds Committee.



The dome specifications are about three weeks away from final reviews. Within five weeks, Walter said public bid letting will begin.

Building and Grounds Committee Chairman David Blankenship said they are hoping to transition from having the encapsulation completed, right into the dome restoration.

[Angela Reiners with photos by Reiners and Bill Walter]

 