Beginning Monday September 20, 2021 at 8:00 AM the second stage of
the resurfacing projects will begin.
Contractors will begin Micro surfacing on Railer Way/Wyatt Ave from
the city limits to Sherman St. as long as the weather permits. If
weather delays work on Monday, work on these two streets will take
place Friday.
• Railer Way & Wyatt Ave. (Monday) Friday if operations are rained
out on Monday.
• Jefferson from 5th St. to Short 11th St. (Tuesday)
• Short 11th from Jefferson to Postville Dr. (Tuesday)
• N. Elm from 8th St. to Woodlawn Rd. (Wednesday)
• Palmer from Woodlawn to Feldman Dr. (Wednesday)
• Nicholson from Lincoln Pkwy to N. Ottawa St. (Thursday)
• N. Ottawa from Nicholson to Keokuk St. (Thursday)
[to top of second column] |
Expect to see intermittent street closures and restricted lanes. Please avoid
these streets while work is taking place. If you have to travel in the area,
please use extreme caution and obey all traffic control signs and Flagger
personnel. Avoid driving on newly resurfaced streets if possible. If you do
travel in these areas, avoid excessive turning when entering or leaving
driveways or side streets.
If there are any questions, please contact the Lincoln Street Department at
217-732-4655.