Wind Farm Road Construction to
start this week in Beason, Chestnut, and Latham area
Send a link to a friend
[May 28, 2024]
The
next phase of roadway construction at the Top Hat wind farm will
begin soon. The project will be located in eastern Logan County in
the area of Beason, Chestnut, and Latham. All the construction will
be south of IL Route 10 and north of IL Route 121.
Road construction is expected to begin in late May and will last
through the Fall. This road construction will provide access to
various wind turbine sites. Approximately 28 miles of roadways will
be strengthened in 2024.
To accommodate these roadway improvements, road closures will be
required over the next few months. Most culvert installations will
be completed with a daytime closure. However, some larger culverts
may require multi-day closures. Asphalt paving on County Highway 6
through Chestnut will be constructed using lane closures. Cement
stabilization on the various roads will require closures that may
last up to 1 week.
Signs and barricades will be erected to inform traffic of these road
closures. Local residents will still have access to their homes.
Construction of the tower foundations is expected to begin later
this year, and erection of the turbines is expected to take place in
2025. A total of 60 wind turbines are expected to be constructed.
Anyone interested in the most current road closure information can
receive daily email updates. To be included on the distribution list
for the initial phase of road construction, please contact Beniach
Construction.
Shannon@beniachconstruction.com
Other project questions for the Top Hat wind farm can be directed to
TopHatWind@
invenergy.com,
or contact Bret Aukamp at the Logan County Highway Department.
[Bret Aukamp]