Kickapoo Creek Park gets a new
flag pole courtesy of Jackson Mathon's Eagle Scout project
Send a link to a friend
[January 23, 2025]
In
the past few years, several scouts have completed Eagle Scout
projects that benefit the community in some way. Jackson Mathon’s
Eagle Scout project is one example.
Community service projects are a requirement for any youth to earn
their Eagle rank. These projects require a significant effort to
complete.
An Eagle Scout planning guide website says these projects require
the scout “to plan, organize, and direct a project of significant
value.” It also provides an “opportunity to demonstrate leadership
qualities.”
Jackson Mathon’s Eagle Project was the flagpole improvement at
Kickapoo Creek Park. It consisted of leveling off the area around
the flagpole, removing the old pole and installing a new one, adding
solar lights, and putting in a landing pad made out of pavers around
the flag.
Mathon said, “I decided that I wanted to do a project of some kind
there multiple years ago, as the people there had been such a great
help to the troop, and the park is one of my favorite places in
general, and I wanted to give back.”
Mathon carefully considered what he wanted to do for
his project. He said, “after spending multiple years looking for
what I wanted to do I had it narrowed down to either clearing out
much of the underbrush and invasive species in the park, or
improving the old and rapidly degrading flagpole.”
The first would be extremely impactful, but Mathon said it would be
very impermanent in nature and was already beginning to be done by
the park's staff as it was.
Because of that fact, Mathon helped with some of that removal
individually, and it may become a service project at some point.
However, for an Eagle Project, Mathon decided improving the flagpole
seemed to be a better idea, as it had a greater perceived impact,
would be longer lasting, and would serve to bring the flagpole back
into accordance with the flag code.
Mathon said, “planning my project began multiple
years ago, but I truly began to complete the paperwork in the late
spring of 2024. Following that, I visited one of the park's board
meetings and presented my plan. After a few questions on the
details, they approved the premise, and I completed the rest of the
paperwork before visiting them again near the end of the summer for
final approval.
After around 15 hours of planning and paperwork, Mathon said the
actual work began. “The week before the project, I surveyed the area
and plotted out what we needed to do.”
Then, Mathon’s dad (Mark Mathon) then loaded their tractor and
dropped it off in the park in order to use it for setting the rough
grade. His dad ran the machine in this case, as scouts are not
allowed to run power tools or gas powered machines.
Next Mathon dug up around the flagpole and pulled the old one, which
was nearing the point of being able to fall. His Dad then used the
tractor to dig the hole necessary to put in the new concrete base,
weighing around 800 pounds. “We then very carefully rolled that into
place and leveled it.”
In the following days, Mathon and his dad drove to
Menards in Forsyth, as they offer a discount on materials for those
completing eagle projects. Following that, it was the first day of
the eagle project, and they had sand delivered to the site.
On Saturday morning of the project, Mathon said
people began arriving and the job truly began.
Eagle projects are less about the work actually completed, and more
about demonstrating planning and leadership. Therefore, Mathon said,
“rather than doing the work myself, my main purpose was coordinating
the work and keeping people safe and on task. I separated people
into three groups, one loading wheelbarrows with gravel, one running
those wheelbarrows up to the pad, and the last group unloading those
wheelbarrows and leveling off the gravel.”
That process continued until there was a level pad of
gravel at a little over three inches thick. Mathon said the process
then repeated again with sand, but after making a circle with a
diameter of around four feet the most tedious process began,
bricklaying.
[to top of second column] |
The landing pad around the base was made up of 681
pavers from a circle kit followed by square blocks to increase the
diameter.
Mathon said it was a very delicate process of
numbering the blocks to follow the pattern, leveling the sand for a
final check, laying the pavers, setting the pavers with a mallet,
checking the final grade to make sure that the pad would drain water
properly, and repeat the process for 13 more rows until all 681
pavers were laid and set.
Four people then went through with screwdrivers and
levels making sure that pavers were level, evenly spaced, and making
the proper grade overall. Next, edging and locking sand was applied
and compacted. Finally, the flagpole and lights were installed, and
the project was complete. Overall, Mathon said planning took around
20 hours over the course of six active months, and the work took two
days, and including my his work around 150 man hours to complete.
As with most projects, there were some costs
involved. Mathon said after proposing the idea to the park board,
they agreed to do it and graciously offered to cover the costs of
materials. Because of this great kindness, he said “I did not need
to do any fundraising.”
While the Logan County Trails Association was perfectly happy to
cover the entire cost, Mathon said, “I could not take that fully
with a good conscience.” Therefore, the cost of the sand, gravel and
pavers were covered by the {park board], while the [Mathon] family
supplied the lights and flagpole. Mathon said, “we were able to buy
a very nice flagpole at an auction for a reasonable price and chose
to donate that to the park through the project.”
Mathon’s project benefited the community as the
appearance of the park was improved and the flag itself was brought
back into the guidelines of the flag code. Additionally, Mathon said
the experience of conducting flag ceremonies, which multiple groups
do throughout the year, is significantly improved.
This project also serves to improve the longevity of the flagpole,
as the new pole and landing pad will last for years to come, serving
to improve the appearance of the park as this project resulted in a
better flagpole and overall larger impact resulting from the
displayed flag from before.
Since the flagpole is likely to be used for years to come by many
people, Mathon’s project will have a lasting impact.
Angela Reiners
|