| Mill & Overlay Street Project 
			Continues
 [July 23, 2025] 
            All the streets have been 
			milled for the 2025 Mill & Overlay Street Project. The contractor 
			will start the asphalt overlay portion tomorrow, the schedule will 
			be as follows. Wednesday July 23, Heritage Ave, Railsplitter Ave and 
			N Union St. Thursday July 24th N Kankakee St, 8th St, and 3rd St. 
			Friday July 25th Chicago St, Wyatt Ave and N Mclean St. Please 
			continue to obey the No Parking restrictions in these areas.
 
 Please avoid these streets if possible. If you must drive on these 
			streets, please drive cautiously and obey construction Personnel and 
			signs.
 
 If you have any questions, please call the Lincoln Street Department 
			at 217-732-4655.
 
 
			