Friday, August 03, 2007
sponsored by Graue Inc. & Illini Bank

Residents and business owners hear construction plans for Fifth Street Road

Send a link to a friend

[August 03, 2007]  A public hearing was held Thursday night for people who live and work along Fifth Street Road between Lincoln Parkway and Interstate 55. The meeting was conducted so that those that most directly affected could hear what changes are planned to the roadway and how construction would affect their normal path of travel.

Project manager Lisa Kramer of Hanson Professional Services in Springfield presented plans, which are in the preliminary stage. She told the audience of about 40 that planners realize it will be an inconvenience to those along the road, but plans have been made to minimize the inconvenience.

The initial study for the roadway was from Lincoln Parkway to New Holland-Middletown.


Drawing: Typical Sections

The portion that is now being planned is from Lincoln Parkway to I-55. This area has been divided into five construction segments. The segments may not go in order of their number and may even hopscotch, Kramer said.

  • Segment 1: I-55 to Forrest Hills Road

  • Segment 2: Forest Hills Road to Connolley

  • Segment 3: Connolley to the closest middle entry to Westminster

  • Segment 4: Middle Westminster Drive to Holly Drive

  • Segment 5: Holly Drive to Lincoln Parkway (This is the longest stretch and as such is expected to take the longest.)


Location

The current road has two lanes, one going each direction, and it is between 20 and 25 feet wide.

The proposed road would be three lanes, with one lane in each direction and a center turn lane, and between 26 and 32 feet wide.

Its construction would be concrete curb and gutter, and a thick asphalt bed that is 8,000-pound weight-tolerant for trucks. The whole crowd chuckled when an audience member jested, "Could we have curb and gutter the other side of I-55 too?"

Water lines are planned to run on the south side and sewer on the north. The location of the storm water line has not been determined.

A possible bicycle path is laid to the south.

Pertinent information during construction:

  • During the construction of each of the five segments there will always be one lane of roadway in place.

  • All emergency vehicles will have access at all times of the day. Everyone not living or doing business in the section that is under construction will be detoured around.

  • Minimal detour routes have been set.

  • Trucks going to businesses in construction areas will still have access.

  • The speed limit will be 35 mph.

  • People living on the other side of I-55 will be detoured during the construction.

  • Each segment is expected to be closed between one and two months.

[to top of second column]

Kramer said that planning began with a study in 1996, and that study has been updated in 2007 for roadway changes, current materials and costs. She anticipates submitting a preliminary design plan and specifications to the Illinois Department of Transportation early in 2009. The review process will last six to 12 months and then, with a finalized plan in hand, construction could begin.

The date for the start of construction is then dependent on the city of Lincoln and Logan County having funding in place. The city is responsible for 75 percent and the county for 25 percent of the costs. Estimated cost at in the preliminary stage is $4.4 million to $4.7 million.

It was of interest to some residents that the plans incorporate extending the sewer line as far as gravity would allow toward I-55. Kramer said that $300,000 to $400,000 has been incorporated in the estimated cost. It is always better to put a sewer line in at the same time as road construction, she said.

The city is hoping for state or federal dollars to help fund the project. If that fails, city treasurer Les Plotner said that they could put it on a referendum to raise the non-home rule sales tax 0.5 cent. They would then take out a loan that would be paid by the non-home rule tax.

The roadway from I-55 to the New Holland-Middletown is planned to remain two lanes. This part of the road falls entirely to the county to fund.

According to Bret Aukamp, Logan County highway engineer, the county does not want to spend the funds to update that plan until funding for the construction is possible.

Preliminary reports, including environmental documents and an engineering analysis with drawings, maps and aerial photography, are available for review and inspection at Lincoln City Hall for the next 10 days.

[Jan Youngquist]

< Top Stories index

Back to top


 

News | Sports | Business | Rural Review | Teaching and Learning | Home and Family | Tourism | Obituaries

Community | Perspectives | Law and Courts | Leisure Time | Spiritual Life | Health and Fitness | Teen Scene
Calendar | Letters to the Editor