This summer Chester-East
Lincoln is going through some upgrades and having some of its parts
polished. A work crew from mechanical contractor E.L. Pruitt,
Springfield, is installing new pipes in the heating system.
Approximately 4,000 feet of 4-inch pipe is being used to upgrade
existing lines in the south and east wings. Original pipes were
underground and had begun to develop leaks. They are being replaced
with overhead lines, hidden above the dropped ceiling. The
eight-week job is on schedule and will be completed by the end of
July.
Allred Floor Service, Morton, has refinished the gym floor. The
janitorial staff is moving furniture in order to clean classrooms.
The building will shine when students return from summer vacation.
Pictures by Marla Blair |
Journeymen Mitch Johnson and Justin Bonner
and foreman Aaron Gurney from mechanical contractor E.L. Pruitt,
Springfield, are installing new pipeline for the heating system at
Chester-East Lincoln.
|
Four thousand feet of pipe, in 20-foot
lengths, is being used to upgrade original, underground heating
system pipes. The new pipeline will be installed above the dropped
ceiling. |
|
|