Japan releases 2020 stadium guidelines,
but no cost estimates
Send a link to a friend
[August 14, 2015]
By Elaine Lies
TOKYO (Reuters) - Japan on Friday approved
guidelines for its new Olympic stadium, vowing to build an "athlete's
first" stadium as cheaply as possible and complete it by March 2020, a
year later than planned, but without including any cost estimates or
limits.
|
Japan scrapped its original plan for the new National stadium last
month in the face of widespread outrage after costs ballooned to
$2.1 billion, nearly twice original estimates -- an unusual move for
an Olympic host city this late in the process.
The International Olympic Committee (IOC) signed off on the decision
for the stadium, centerpiece of the 2020 Summer Olympics, but it has
also said it will be part of the new stadium tender to make sure
things stay on track.
The guidelines approved by Prime Minister Shinzo Abe and other
officials late on Friday emphasized keeping costs as low as possible
but included no upper limits or estimates. Plans are for management
of the stadium to be handed over to a private firm once the Olympics
are over.
"We should make a structure that will emotionally move people all
over the world," Abe said.
"Of course, keeping costs down is a priority, and we must make the
best, realistic plan we can.
Construction will be completed by March of 2020, the plan said, a
year later than originally planned. Media reports have said
construction will not begin until the end of 2016 or the beginning
of 2017, also at least a year behind the original schedule.
Cost estimates will be set in a later plan to be released later this
month or early in September, but officials have said their aim is to
do everything as cheaply as possible, including having a roof over
spectator seats only.
The stadium will be built to host rugby, athletics and soccer,
leaving Japan with the ability to bid for World Cup soccer in the
future. A number of the required 80,000 seats will be temporary.
An international competition will be held to choose a new design
later this year, and a decision is due on both design and
contractors in January 2016, media reports have said.
[to top of second column] |
Japanese officials have acknowledged the original design for the
stadium by U.K.-based Zaha Hadid Architects may have helped them win
the Olympics, but the futuristic plan -- likened to a bicycle helmet
-- drew fire for its grandiose size and what critics said was a lack
of fit with its site.
Japan pinned blame for the ballooning price tag on the stadium
design, but the architects countered that construction costs have
been soaring in Tokyo, that they had made changes several times to
bring costs down and that Japan's decision to scrap the plans came
without any warning.
Tokyo has already paid out around 6.2 billion yen ($49.84 million)
to Hadid, other architects and construction firms, prompting Abe to
apologize on Monday for wasting tax money.
Preparations for the Olympics, Tokyo's second time to host the
sports extravaganza, have run into hurdles on a number of fronts,
including ballooning overall costs and rolling back promises of
having most venues within eight kilometers of the Olympic Village.
Even the Olympic logo has become the focus of plagiarism
accusations, which Japan and its designer deny.
($1 = 124.4000 yen)
(Editing by Greg Stutchbury/Sudipto Ganguly)
[© 2015 Thomson Reuters. All rights
reserved.]
Copyright 2015 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
|