Seattle's
long-broken tunnel-boring machine set to resume Nov. 23
Send a link to a friend
[July 18, 2015]
SEATTLE (Reuters) - The world's
largest-diameter tunneling machine could resume drilling under downtown
Seattle in late November after repairs are completed, allowing a central
part of a years-delayed highway project to go forward, Washington state
officials said on Friday.
|
The broken machine, known as Bertha, stopped working in December
2013 after digging just 10 percent of a planned tunnel to replace an
aging waterfront highway. It was stuck for more than a year
underneath downtown Seattle.
The new timeline for replacing the busy Alaskan Way Viaduct and
opening it to drivers is now spring 2018, Washington state
Department of Transportation said in a statement. The viaduct was
damaged in a 2001 earthquake and is nearing the end of its lifespan.
"Tunneling is slated to resume in late November, with the machine
emerging at the north end of downtown approximately one year later,"
the Transportation Department said. "The state is not able to verify
the contractor's schedule."
Previously, project contractor Seattle Tunnel Partners said it hoped
to have Bertha drilling again by August, but it pushed that estimate
by nearly four months to Nov. 23, according to a timeline provided
to the state.
In March, crews hoisted Bertha's 2,000-ton front end from a pit in
an attempt to assess damages and make repairs and improvements,
which are scheduled to wrap up in the fall.
[to top of second column] |
Bertha's breakdown and other unexpected construction issues have
left the $3.1 billion project two years behind schedule and sparked
concern about even greater cost overruns. The project had initially
been slated to cost $2 billion and be completed by 2015.
(Reporting by Eric M. Johnson; Editing by Eric Beech)
[© 2015 Thomson Reuters. All rights
reserved.]
Copyright 2015 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed. |