"To the extent that we could accommodate uncertainty and risk, or
reduce risk, we are much better postured today than when we have
tried this in the past," said Pat Shanahan, who oversees production
at the world's biggest planemaker.
Boeing's production lines face a crucial test as the company
prepares to lift output of its bestselling jet by 24 percent while
simultaneously shifting to a new fuel-saving model, the 737 MAX.
Boeing has not attempted such a production boost and model shift
since 1997, when it was forced to stop assembly of its 747 jumbo and
delay building a new version of the 737 for several weeks due to
parts shortages. Boeing was also distracted by a merger with
McDonnell-Douglas at the time.
This time, with zero room for error on the 737, a major cash
generator for the company, Boeing is taking a fresh look at the way
it builds jets by adding more automation.
"When I think about the mistakes we made back then, we didn't have
an integrated plan that included the supply chain," Shanahan said,
noting that the company now follows such a plan.
Shanahan, 52, is a troubleshooter credited with turning round the
787 Dreamliner in 2008 after delays also blamed on supply chain
problems and a missile defense project.
As senior vice president for airplane programs, he must ensure the
737 makeover goes smoothly, and prepare a production system for the
larger 777X, a revamped model of the 777 due to enter service in
2020.
Boeing builds 42 medium-haul 737s a month and plans to lift this to
52 by 2018 in competition with Europe's Airbus <AIR.PA>.
Industry sources have said Boeing is assessing whether the supply
chain can support an increase to 58, but the company says it has
nothing to add to its announced target of 52.
Shanahan declined to discuss further 737 output increases, but he is
prepared to use bold numbers to illustrate the scale of the
industrial challenge posed by the 737, and his belief that
innovation is about production systems, not just aircraft design.
[to top of second column] |
"I talk about 100 (737s a month)," he said, adding, "It is not about
the number...When we said 10 787s a month nobody could get their
head around it. I remember on the 737 program we said one a day.
(People said) 'No way!' Now it is two a day."
Other than the pressures of adding a newer 787-9 variant, the 787
supply base is "starting to stabilize," Shanahan said.
"We are doing a lot of (787) -8s and -9s, so we are stressing that
part of the system until it gets capable. But nothing is in the
abnormal range."
Some in the industry remain concerned that Boeing isn't moving
quickly enough in reducing 787 costs and increasing productivity.
The aerospace industry's wider supply chain always flashes 'red' but
is broadly coping with faster production, Shanahan said. "For the
major elements of the industry it is sound; it is just going through
the stress of growth," he added.
One exception is a chronic shortage of seats that affects most plane
makers. With so many new types being produced, lead times have risen
well above two years. "It drives me crazy," Shanahan said.
(Reporting by Tim Hepher and Alwyn Scott; Editing by Christian Plumb
and Miral Fahmy)
[© 2015 Thomson Reuters. All rights
reserved.] Copyright 2015 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
|