The power struggle pits a handful of farm families and rural residents against
Nextera Energy Resources, a Florida-based renewable energy developer vying to
build the second biggest solar installation in the state.
“It’s kind of a David versus Goliath story,” said Janelle Geurts, who grew up on
the Lyon County farm she works with husband John. “You just sit here and try to
exhaust every effort you can, which we are trying to do. But they’ve got every
angle covered, let’s put it that way.”
Nextera needs approval from the Minnesota Public Utilities Commission to plant
more than 200,000 photovoltaic panels on land where crops are currently being
harvested for what could be the last time. The developer cites the economics of
scale as the reason for the super-sized, by Minnesota standards, project. The
sun power would tie into Xcel Energy’s transmission lines near Marshall, helping
the utility meet a state mandate for 1.5 percent of retail electricity to be
solar by 2020.
“The team continues to stay engaged with both local and state officials as well
as the community and is confident the project, if approved, would have a
positive impact on the local economy,” Steve Stengel, Nextera Energy Resources
communications director, said in a statement.
At an October 20 and 21 hearing, an administrative law judge will consider the
applicability of a state regulation restricting the amount of acreage classified
as prime farmland under federal standards that can be taken for electric
generation.
“To me, it doesn’t make much sense, to have what is supposed to be a green
policy, and a very un-green proposal, in my mind, by Nextera,” said Court
Anderson, a Minneapolis attorney who represents several landowners.
RELATED: Timeout! Minnesota city passes moratorium on solar craze
The rule prohibits power plants from using more than one half acre of prime
cropland per megawatt of capacity. The formula limits the 62 megawatt proposed
facility to 31 acres, far fewer than the 364 acres planned for the solar array.
But a provision allowing for approval of projects in areas without “a feasible
and prudent alternative” complicates everything.
[to top of second column] |
“It would be impractical to site a similarly sized large solar
project (even assuming land could be acquired) within this area
without impacting prime farmland,” Nextera Director of Development
Brandon Stankiewicz said in testimony filed with the state. “… Prime
farmland is the predominant land type in this region of the state.”
A state environmental review of the proposed 515 acre site
identified 187 acres of designated prime farmland, along with 290
more acres that would qualify, if drained. That amounts to one-tenth
of one percent of the county’s 386,000 acres of farmland. The land
could revert to agricultural purpose after the project’s likely
25-year lifespan.
“The change in land use would result in a small annual loss of
overall crop production in Lyon County … and in the state
generally,” according to the Marshall Solar Energy Project
Environmental Assessment from the Minnesota Department of Commerce.
While property values, aesthetics and other issues concern
opponents, the loss of agricultural land tops their list. Residents
also argue that plenty of alternative sites exist in neighboring
counties with less valuable land.
“I think something has got to be in place going forward to protect
our natural resources, before we go and start gobbling it up here
and all of a sudden go, gosh, what did we just do?” Geurts said.
Ten family farms reside within a mile of the project’s footprint,
some just hundreds of feet from the planned solar fields.
“There’s some days, you look out across the buildings and you just
start crying, thinking, I’ve busted my hump on my property to get
what I’ve got and they’re destroying it,” said Chuck Muller, who
would see a field of solar panels from his deck. “And then the next
time, you could look and you get so mad, you could bite nails in
half.”
The PUC board will consider the administrative law judge’s
recommendation in deciding whether to approve the project, likely in
January 2016. Nextera hopes to build and begin operating the solar
facility in 2016.
Click here to respond to the editor about this article
|