Bridge Repair Project on County Highway 9
Primm Road south of Lincoln to be closed through November
 

Send a link to a friend  Share

[August 25, 2016]  LINCOLN - A bridge repair project is being planned for County Highway 9 (Primm Road) over Salt Creek approximately 6 miles south of Lincoln, between 950th and 1000th Street. During construction the road will be closed to traffic.

The project is scheduled to begin on September 6th and is expected to last thru November.

The project was awarded to Sangamo Construction located in Springfield, Illinois. The cost of the project is approximately $378,000. Funding will come from Logan County’s allotment of federal transportation funds.

Cooperation and patience is always appreciated during the construction season as we continue to improve the safety of our roads and bridges.

[The Logan County Highway Department]
 

Back to top