With Dakota denial, outlook for U.S.
pipelines turns murky
Send a link to a friend
[December 05, 2016]
By Liz Hampton
HOUSTON (Reuters) - The U.S. Army's denial
of an easement for the Dakota Access Pipeline, after permitting and
legal obligations were followed, sets an uncertain precedent for new
projects despite President-elect Donald Trump's promise to support
energy infrastructure.
The decision came after months of protests by the Standing Rock Sioux
tribe and others who said the line could desecrate tribal grounds, or a
spill could contaminate drinking water.
While most of the 1,172-mile (1,885-km) pipeline is complete, Energy
Transfer Partners <ETP.N>, the line's owner, needed an easement from the
U.S. Army Corps of Engineers (USACE) to drill under Lake Oahe. The lake,
a water source formed by a dam on the Missouri River, has been the focus
of protesters.
The Army's intervention sets an unsettling precedent, analysts and
industry groups told Reuters, because Energy Transfer had undergone the
necessary environmental reviews and permitting processes to move ahead
with construction.
"I think it sends a horrible signal to anyone wanting to invest in a
project and I strongly suspect those policies will be discontinued on
Jan. 20th," said Brigham McCown, the former head of the U.S. Pipeline
and Hazardous Materials Safety Administration (PHMSA) under George W.
Bush, referring to the inauguration of President-elect Donald Trump.
Still, the decision to deny the easement tempers some of the optimism
pipeline companies assumed following the election of Trump, who is seen
as more supportive of oil and gas projects.

Energy Transfer Partners said in a statement the decision was
politically motivated and it did not intend to reroute the line.
(For graphic on the Dakota Access Pipeline, click
http://tmsnrt.rs/2cqkRJ7)
DELAYS & RISING COSTS
Beyond the federal approval issues, state and local governments have
also mobilized against pipelines. Earlier this year, Georgia's state
legislature passed a bill to restrict pipeline developments, stopping a
gasoline line from Florida to South Carolina from being built.
Energy Transfer chief executive Kelcy Warren, a donor to Trump's
campaign, said his election was a positive. Last week Trump for the
first time voiced support for the Dakota Access project.
Trump has also said he would support TransCanada Corp's <TRP.TO>
Keystone XL, which the Obama Administration rejected last year.
Denying permits for an already-approved pipeline adds a new level of
uncertainty to projects. Oil companies have already been facing growing
resistance from environmental groups that have resulted in delays or
unanticipated costs.
[to top of second column] |

Native American "water protectors" celebrate that the Army Corps of
Engineers has denied an easement for the $3.8 billion Dakota Access
Pipeline inside of the Oceti Sakowin camp as demonstrations continue
against plans to pass the Dakota Access pipeline adjacent to the
Standing Rock Indian Reservation, near Cannon Ball, North Dakota,
U.S., December 4, 2016. REUTERS/Lucas Jackson

Equipment used for the Dakota Access line has been set on fire, and
in October, a group of protesters turned off valves on pipelines
transporting oil from Canada to the United States. Together, those
lines had capacity to move some 2.8 million barrels per day of oil.
"Until you see that Trump has a track record of approving things and
showing that things can get built in time, it's tough to say it's
not a murky environment for pipelines," said Sarp Ozkan, manager of
energy analytics for Drillinginfo.
That means pipelines could face higher risk premiums and have a
harder time getting volume commitments from shippers that underpin
such projects, Ozkan said.
Energy Transfer has said it expects to lose almost $84 million each
month the Dakota Access pipeline is delayed, and that losing
shippers could result in its cancellation, according to a court
filing.
"I think midstream companies will hope that each project can be
decided based on necessary permitting approvals, but there will be
increased risk where agencies like USACE are involved," said Sandy
Fielden, director of research in commodities and energy at
Morningstar.
While the Standing Rock Sioux have said they would support a
rerouting of the line, others, such as the Indigenous Environmental
Network (IEN), want it canceled.
"Given Trump's support of the Dakota Access, and the Keystone XL, we
remain cautious," said Dallas Goldtooth, a spokesman for IEN.
(Reporting by Liz Hampton in Houston; Editing by Tom Hogue)
[© 2016 Thomson Reuters. All rights
reserved.]
Copyright 2016 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
 |