Exclusive: Chevron's
giant Australia LNG plant facing union calls for safety
checks
Send a link to a friend
[July 21, 2016]
By Sonali Paul, Oleg Vukmanovic and Ron Bousso
MELBOURNE/MILAN/LONDON - (Reuters) -
Forced to shut its $54 billion Gorgon liquefied natural gas (LNG)
export plant twice in its first five months, Chevron Corp now faces
calls from union officials for a probe into the site's safety.
Chevron denies there have been any safety breaches at the plant but
is under pressure to resolve problems that have limited exports to
just two cargoes since starting operations in March.
The Australian Manufacturing Workers' Union (AMWU) has told Reuters
it has formally requested access to the site.
"The AMWU has concerns about safety at Gorgon," Steve McCartney,
West Australian secretary of the AMWU, told Reuters via email.
A failed weld on a valve casing called a trunnion caused the gas
leak that forced the plant to close on July 1, he said.
"The AMWU wants to know why it failed, and what checks were carried
out to ensure it met Australian standards," McCartney said.
Chevron called the leak "minor", although it did evacuate some
workers. On Wednesday the company said it expected to resume
production shortly.
"Chevron Australia is in discussions with the AMWU to visit the site
as part of usual union engagement with its members," a spokeswoman
said, adding that there had been no safety breaches at the plant.
Reuters could not independently confirm whether the issues at the
plant pose any risk to worker safety.
MISTAKES
Chevron, which is counting on Gorgon to help it become an LNG leader
in Asia, reported its first shutdown in April and was forced to shut
again following a gas leak on July 1.
In interviews with Reuters, site workers and industry sources
familiar with operations at Gorgon said mistakes led to the first
shutdown.
According to information provided by one engineer at the plant,
liquid propane in the refrigerant circuit flooded into a section of
pipeline meant to handle gases only.
Metal debris inside the piping was propelled along at speed,
damaging equipment and producing "very loud clunking noises" which
prompted operators to initiate emergency shutdown procedures,
according to one worker and corroborated by AMWU's McCartney.
Chevron said the problem occurred in the propane refrigerant circuit
where natural gas is cooled into a liquid but declined to provide
further details.
LAGGING RIVALS
The shutdowns have cost Gorgon more than $200 million in lost
output, excluding repairs and other expenditures, one industry
consultant estimated, basing the figure on an export schedule of
around one cargo per week.
The outages have also contributed to a jump in global LNG spot
prices, which are up by around 40 percent since April. [LNG-AS]
Two industry sources said Chevron ignored advice from project
partners Royal Dutch Shell and Exxon Mobil to go slow with the
launch of Gorgon.
[to top of second column] |
An undated handout photo of Chevron's Gorgon LNG project located in
Western Australia. REUTERS/Chevron/Handout via Reuters
"We do not comment on industry rumor or speculation," Chevron said. Royal Dutch
Shell and Exxon also declined to comment.
"Gorgon's teething issues mirror the ongoing problems at Angola LNG and put the
spotlight on Chevron," said Rystad Energy analyst Readul Islam regarding
Chevron's ability to deliver LNG plants.
Chevron and partners BP, ENI and Total has just finished work on its LNG plant
in Angola following a two-year shutdown to fix design flaws.
Operations tentatively resumed at the plant just last month.
Meanwhile, rivals have moved forward, with Exxon Mobil launching its Papua New
Guinea (PNG LNG) liquefaction plant on time and on budget in 2014, when Gorgon
was first due to start operations.
"The relatively niggle-free ramp-up of Gladstone LNG (in Australia) as well as
the PNG LNG trains over the past two years could lead to questions being asked
of Gorgon's onshore (start-up) team," said Rystad's Islam, but he added that
Gorgon's greater complexity and size arguably make it a bigger challenge.
Industry sources and analysts continue to project start-up delays at subsequent
phases of Gorgon due partly to the latest hiatus.
Chevron denies this. It says that construction on Gorgon production lines two
and three, which will boost its export capacity to 15.6 million tonnes a year in
2017, are unaffected.
Peter Coleman, chief executive of Woodside Petroleum which is partnered with
Chevron in developing the $33 billion Wheatstone LNG project in Australia, said
his company was taking a more hands-on role in development as Chevron is "having
to direct resources elsewhere".
But he added he had no concerns about Chevron as a project operator.
"They've got a lot on their plate and so many hands help, and that's where we
are at the moment," he said.
(Additional reporting by Sarah McFarlane in London and Ernest Scheyder in
Houston; writing by Oleg Vukmanovic; editing by Jason Neely)
[© 2016 Thomson Reuters. All rights
reserved.] Copyright 2016 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed. |