[September 30, 2016]
By Nick Carey
(Reuters) - A deadly commuter train crash
in Hoboken station in New Jersey renews focus on a mandatory
anti-collision system that has been plagued with lengthy, contentious
delays.
Officials said train operator New Jersey Transit has not installed the
positive train control (PTC) system in Hoboken or anywhere else on its
network.
PTC works by hitting the brakes on a train if the engineer misses a
signal to halt - the equivalent of running a red light. How long it
takes a train to stop depends on its weight. Freight trains can take up
to 2 miles to stop. The system combines GPS, wireless radio and other
technologies, making it far more complex than originally envisioned and
requires more investment and time to make it work, according to railroad
companies.
By law, NJ Transit is required to have a system in place by the end of
2018. Amtrak has rolled out PTC on its network, while the freight
railroads have mostly been rolling out the technology a section of track
at a time.
Thursday morning's rush-hour crash killed at least one person and
injured 108 others.
National Transportation Safety Board vice chair T. Bella Dinh-Zarr said
at a news conference in Washington that the board would "absolutely"
look at whether the lack of PTC was a factor.
"PTC has been one of our priorities," she said. "We know that it can
prevent accidents."
It is unclear how fast the train in Hoboken was traveling or whether a
PTC system would have prevented an accident.
Former NTSB managing director Peter Goelz said that PTC is most
effective at higher speeds out on open track, adding it is far from
clear it could have made a difference in Hoboken.
Goelz said other factors, such as the alertness of the locomotive
engineer, could turn out to be more important.
The NTSB said it would also look for similarities with another crash at
the Hoboken station in 2011, when a commuter train struck the bumping
post at the end of the track, injuring 30.
Last year, neighboring New York's Metropolitan Transportation Authority
received nearly $1 billion in federal loans to implement PTC on its two
commuter lines, although it was criticized last month by the federal
agency that issued the loan for making almost no progress in installing
the system.
New Jersey Transit ranked second for the most train accident reports
nationwide for commuter railroads from January 2007 through June 2016,
behind Amtrak.
New Jersey Transit had 271 accidents, or 18 percent of the total,
compared to Amtrak’s 44 percent, according to data from the U.S. Federal
Railroad Administration Office of Safety Analysis.
The rankings in part reflect the heavy use of rail transit in the U.S.
Northeast compared to other parts of the United States.
According to a report by NJ Transit to the Federal Railroad
Administration for the first half of 2016, the public transport system
does not have PTC in operation on its 326-mile network.
[to top of second column] |
A derailed New Jersey Transit train is seen under a collapsed roof
after it derailed and crashed into the station in Hoboken, New
Jersey, U.S. September 29, 2016. REUTERS/Carlo Allegri
None of the 1,100 New Jersey Transit employees who will need
training to operate PTC have yet received it, the report said.
White House press secretary Josh Earnest said Thursday "it is too
early to tell" whether positive train control would have prevented
the crash.
New Jersey Governor Chris Christie said the train was moving much
too fast when it came into the station.
"We don't know what the cause of the high rate of speed was," he
said.
PTC was mandated by Congress in September 2008, after a Metrolink
train ran a stop signal in Los Angeles and hit a Union Pacific
freight train, killing 25 people. Federal investigators faulted the
commuter train's engineer, who was sending text messages while on
duty.
Last year, the major U.S. freight railroads successfully lobbied for
a three-year extension of the December 2015 deadline for
implementing PTC, with the option to apply for two one-year
extensions. Several railroads have said that they will need both
extensions to fully implement PTC.
In June, Lance Fritz, chief executive of No. 1 U.S. railroad Union
Pacific Corp told Reuters the company would have the system fully
installed on its 32,000-mile network, but would need the extra two
years to "debug" it.
While critics say the railroads are dragging their feet on PTC, the
railroads say they have spent more than $6 billion on PTC so far and
expect to spend $4 billion more to complete implementation.
John Ireland, a project manager at Arlington, Virginia-based
railroad consulting firm R.L. Banks & Associates, said cash-strapped
public transport operators face a dilemma: They are under pressure
to implement PTC while struggling to maintain crumbling
infrastructure and handle rising passenger numbers.
"Even the major for-profit freight railroads with their tremendous
resources have had a hard time installing PTC," Ireland said. He
said putting in the system was "a real scramble" for public
transportation agencies because "they operate at a loss and they are
not a budget priority for governments in most regions."
(Reporting by Nick Carey in Chicago; Additional reporting by David
Shepardson in Washington and Jeffrey Dastin in New York; Editing by
Eric Effron and Grant McCool)
[© 2016 Thomson Reuters. All rights
reserved.]