Exclusive: U.S. agency claims huge hole
in Westinghouse's pension plan
Send a link to a friend
[September 23, 2017]
By Tom Hals
WILMINGTON, Del. (Reuters) - Employees of
U.S. nuclear power firm Westinghouse Electric Co LLC, which is bankrupt
and reeling from a failed reactor project, got a nasty surprise
recently: in the eyes of the U.S. government's pension insurer, its
retirement plan has a massive shortfall.
While bankrupt companies often have big pension deficits, the vast
majority flag the underfunding years in advance of filing for Chapter
11. By contrast, the Westinghouse Electric Co Pension Plan, which has
about 9,700 participants, appeared fully funded in its most recent
report to the Department of Labor in 2015.
The Pension Benefit Guaranty Corp estimated the pension plan is unfunded
by $937 million, according to previously unreported court filings in
August.
The shortfall is conditional on Westinghouse using the tools of
bankruptcy to terminate the plan. In that case, the PBGC would step in,
take over the plan and apply its more conservative accounting.
Westinghouse spokeswoman Sarah Cassella said the company has not told
the agency it will end the plan.
Westinghouse is considering bids for the company, and has asked
potential buyers to assume the pension would be maintained and that
annual contributions would continue near current levels, according to a
person familiar with the bidding process.
However, Pittsburgh-based Westinghouse, which is owned by Toshiba Corp
<6502.T> of Japan, is expected to attract private-equity investors who
tend to want as few obligations as possible.
One actuary who advises pension plans said the PBGC claim may encourage
buyers to insist Westinghouse terminate the plan.
"It highlights the poorly funded status and so no one really wants to
take on the defined benefit plan," said Greg Reardon, of consulting firm
Cheiron Inc.
POTENTIAL DISCONTENT
The PBGC claim exceeds the plan's $926 million in assets and according
to PBGC data it would be among the 10 largest for a pension shortfall,
ranking ahead of Trans World Airlines in 2001 and Pan American Air in
1991 and 1992.
The claim stems not from mismanagement or fraud, but the way
Westinghouse and the PBGC determine how much is needed today to pay for
future pension benefits.
Under Department of Labor rules, Westinghouse is required to assume that
a bond portfolio will earn a much higher rate of return than the current
market rates, which are used by the PBGC.
[to top of second column] |
The Vogtle Unit 3 and 4 site, being constructed by primary contactor
Westinghouse, a business unit of Toshiba, near Waynesboro, Georgia,
U.S. is seen in an aerial photo taken February 2017. Georgia
Power/Handout via REUTERS
The agency's conservative approach means more money is needed today
to pay for retirees. As a result, PBGC claims in bankruptcy cases
often catch other creditors off guard, said Joseph House, a
principal at Palisades Capital Advisors and former head of the
PBGC's restructuring group.
The company has said in court documents that retaining highly
specialized engineers is key to its success, and until it filed for
bankruptcy in March the pension was one way to hold on to top
talent.
Ending the plan would mean more Westinghouse debt and less for other
creditors, and it could mean reduced benefits for the plan's
participants. If the plan is terminated, participants will receive a
guaranteed benefit from the PBGC, which currently hits a maximum at
about $64,000 a year. Any annual pension payments above that level
could be lost, although there are exceptions.
A former Westinghouse executive, who asked not to be identified
talking about his former employer, said the PBGC claim came as a
shock, given the plan's funding levels in recent years and
conservative investments. "You're going to have a lot of
discontent," said the executive. "It's a great tool to keep people
tied to the company."
Westinghouse, however, is in cost-cutting mode. The company said in
its recent turnaround plan it would reduce its roughly 11,000 global
staff by 7 percent.
In July, two utilities in South Carolina canceled a half-finished
nuclear power plant that was meant to be a showcase for
Westinghouse's engineering and design.
The South Carolina project and a similar half-finished plant in
Georgia were both billions of dollars over budget and years behind
schedule, which contributed to Westinghouse's bankruptcy.
(Reporting by Tom Hals in Wilmington, Delaware; Editing by Noeleen
Walder and Nick Zieminski)
[© 2017 Thomson Reuters. All rights
reserved.]
Copyright 2017 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
|