Renewable energy investors see opportunity in Puerto
Rico's demolished grid
Send a link to a friend
[September 30, 2017]
By Valerie Volcovici and Nichola Groom
WASHINGTON/LOS ANGELES (Reuters) -
Hurricane Maria destroyed Puerto Rico's antiquated and bankrupt
electrical system, leaving millions in the dark and utility crews
scrambling to help.
Now some politicians and renewable energy investors see a golden
opportunity in the crisis to use federal funds to re-invent the U.S.
territory's grid as a storm-resistant network that relies less on costly
coal and oil imports and more on local wind, solar, and batteries.
If it happens, it could ease power bills on an island that struggles
with the second-costliest electricity in the United States, behind
Hawaii, as well as infrastructure prone to failing in the region's
frequent hurricanes.
"We cannot waste the opportunity of this crisis and federal aid
package," said Ramon Luis Nieves, a Puerto Rican politician in the
Popular Democratic Party, who headed the island's senate energy
committee until his term expired in January.
"We need to focus on not only getting the grid back up, but improving it
so it can tolerate more renewable energy."
A set of bills introduced this week by U.S. Democratic Senator Ron Wyden
of Oregon would call on the Department of Energy to make the U.S.
electric grid hardier against natural disasters, and would offer grants
for small scale, grid connected solar and other projects.
A Wyden aide said Puerto Rico's utility, the Puerto Rico Electric Power
Authority (PREPA), could apply for such grants to modernize the grid, or
get funds from the Federal Emergency Management Agency to rebuild and
then apply for the grants to help pay for upgrades.
Efforts to reach a PREPA official were not successful.
That government support would be crucial. PREPA was $9 billion in debt
before declaring bankruptcy in July. Its equipment was already "degraded
and unsafe," according to a draft fiscal report the company filed in
April.
Around half of Puerto Rico's electricity is generated from imported fuel
oil, with another third coming from natural gas, and much of the rest
from coal, according to the Department of Energy.
Renewables supply about 2.4 percent, though the island has set a goal to
obtain 20 percent of its electricity from renewables by 2035.
[to top of second column] |
Power lines are seen near Guayama after Hurricane Maria, in Puerto
Rico, September 29, 2017 REUTERS/Alvin Baez
FUTURE GRID
The prospect of a new grid in Puerto Rico has some renewable energy companies
and investors interested. Jeff Ciachurski, CEO of Greenbriar Capital, a
renewable energy investor in Puerto Rico, California and Arizona, said
government support could open up new opportunities for the sector to take over
market share.
"The federal government is in the driver's seat," he said.
Sunnova, a residential solar installer with 10,000 customers in Puerto Rico,
said it was working with the governor to try to restore power off-grid in the
short-term, but said the destruction also creates an opportunity to create a
new, renewable-friendly grid.
"Everybody can agree that what the future and the new power industry and system
look like is not what was there before," John Berger, Sunnova CEO, told Reuters.
Tesla, meanwhile, is sending hundreds of batteries that can store power
generated by solar panels to Puerto Rico to provide emergency help in the wake
of Maria. A company spokesperson did not say what Tesla's future plans were.
On Friday, Puerto Rico Governor Ricardo Rossello said his team is looking at
alternative ways to bring power back on the island, including by using
microgrids, small power networks that can work independently of the main grid.
Judith Enck, a former Environmental Protection Agency regional administrator for
Puerto Rico, said solar-powered microgrids, as well as buried power lines, could
allow for a more rapid recovery after storms.
Hurricane Maria left the entire island and its 3.4 million residents without
power and destroyed 80 percent of its transmission and distribution
infrastructure, according to the Department of Energy.
The Army Corps of Engineers has been placed in charge of restoring power as
quickly as possible, a key step to restoring other basic services like water,
fuel, and food.
(Reporting by Valerie Volcovici and Nichola Groom, Editing by Richard Valdmanis
and Rosalba O'Brien)
[© 2017 Thomson Reuters. All rights
reserved.] Copyright 2017 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed. |