NASA commercial crew program for space
station faces delays, report says
Send a link to a friend
[July 12, 2018]
By Joey Roulette
ORLANDO, Fla. (Reuters) - Plans to launch
the first NASA astronauts since 2011 to the International Space Station
from the United States look set to be delayed due to incomplete safety
measures and accountability holes in the agency's commercial crew
program, according to a federal report released on Wednesday.
SpaceX and Boeing Co are the two main contractors selected under the
National Aeronautics and Space Administration's commercial crew program
to send U.S. astronauts to space as soon as 2019, using their Dragon and
Starliner spacecraft respectively.
But the report from the Government Accountability Office said the issues
could cause delays in the launch of the first crewed mission from U.S.
soil by a private company and could result in a nine-month gap in which
no U.S. astronauts inhabit the ISS.
"Boeing and SpaceX continue to make progress developing their crew
transportation systems, but both contractors have further delayed the
certification milestone to early 2019," the report said.
"Without a viable contingency option for ensuring uninterrupted access
to the ISS in the event of further commercial crew delays, we concluded
that NASA was at risk of not being able to maximize the return on its
multibillion dollar investment in the space station," it added.
Boeing said it was aiming for test flights this year.
"Boeing is working with NASA to ensure that the CST-100 Starliner flies
at the earliest time it is safe to do so," Boeing senior spokesman Jerry
Drelling told Reuters in an email.
Officials with SpaceX, formally known as Space Exploration Technologies,
and NASA could not immediately be reached to comment.
[to top of second column]
|
SpaceX spacecrafts the Dragon (L) and the DragonRider sit on display
at the SpaceX facility in Hawthorne, California June 14, 2012.
REUTERS/Bret Hartman/File Photo
In 2014, SpaceX and Boeing respectively received $2.6 billion and
$4.2 billion contracts to build crew transportation systems under
the commercial crew program, NASA's flagship campaign to use the
private sector for ISS missions.
In the report, NASA said it was working closely with its commercial
partners to resolve the issues and was developing contingency plans
in case of further delays.
Before SpaceX and Boeing can launch the astronauts they must
demonstrate their crew systems are safe for human spaceflight,
according to NASA.
The GAO said it is tracking potential safety risks on the private
companies' crew capsules, including a Boeing Starliner abort system
meant to eject the capsule from a hazardous rocket explosion, and a
since-upgraded fuel valve on SpaceX's Falcon rocket that triggered a
costly 2016 launchpad explosion.
Since 2011, NASA has bought seats on the Russian Soyuz spacecraft
months in advance to send U.S. astronauts to the space station from
launchpads in Kazakhstan. U.S. launches before 2011 were handled by
NASA.
(Reporting by Joey Roulette; editing by Ben Klayman and Rosalba
O'Brien)
[© 2018 Thomson Reuters. All rights
reserved.]
Copyright 2018 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content.
|