Regulator ties pipeline work to deadly
Massachusetts gas explosion
Send a link to a friend
[October 12, 2018]
By Liz Hampton
HOUSTON (Reuters) - A NiSource Inc
affiliate failed to require contract repair crews to relocate pressure
sensors during natural-gas pipeline work, the National Transportation
Safety Board (NTSB) said on Thursday, resulting in overpressured lines
that caused explosions and fires in three Massachusetts communities last
month.
Overpressurized gas poured through Columbia Gas Co of Massachusetts'
distribution system in Lawrence, North Andover and Andover, flooding
into homes and businesses and sparking explosions and fires that killed
one person and injured 21.
Critical valves controlling the gas flow were not shut for nearly 3-1/2
hours after the first alarm was raised at Columbia Gas's monitoring
center, NTSB said in a preliminary report. The center had no ability to
remotely open or close valves on its own, but did notify technicians, it
added.
NiSource is fully cooperating with the NTSB, Chief Executive Joe Hamrock
said in a statement on Thursday. However, it will not comment on the
cause of the incident until the NTSB completes its work, he added.
The incident raised safety concerns about the sprawling U.S. networks of
aging pipelines. The September explosions and fires damaged 131 homes
and businesses as Columbia Gas was replacing cast-iron pipe with safer
plastic lines when the accident occurred.
The NTSB laid out the timetable of events in a dry account of the
company's activities that day.
Crews were working for Columbia Gas in Lawrence, a city northwest of
Boston, to replace an aged cast-iron main with a new plastic
distribution main line. The abandoned main had regulator sensing lines
used to detect pressure in the system.
After that main line was disconnected, the sensing lines lost pressure
and the regulators fully opened, "allowing the full flow of
high-pressure gas into the distribution system supplying the
neighborhood," the report said.
[to top of second column]
|
A Columbia Gas of Massachusetts crew works in a neighborhood
evacuated following a series of gas explosions in Lawrence,
Massachusetts, U.S., September 14, 2018. REUTERS/Brian Snyder/File
Photo
Columbia Gas had approved a "work package (that) did not account for
the location of the sensing lines or require their relocation to
ensure the regulators were sensing actual system pressure,"
according to the NTSB.
Minutes before the explosion, Columbia Gas' monitoring center in
Columbus, Ohio, received high pressure alarms for its South Lawrence
gas pressure system. The company shut down the regulator at issue
about 25 minutes later, around 4:30 p.m, the NTSB said.
September's explosion was the largest U.S. natural gas pipeline
accident since 2010 in terms of structures involved. Eight years
ago, an interstate gas transmission line operated by Pacific Gas and
Electric Company ruptured in San Bruno, California, killing eight
people, destroying 38 buildings and damaging 70 others, according to
the NTSB.
Columbia Gas has said all cast iron and bare steel piping in
affected neighborhoods will be replaced with high pressure plastic
mains that have regulators at each service meter.
(Reporting by Liz Hampton; Editing by Leslie Adler and Richard
Chang)
[© 2018 Thomson Reuters. All rights
reserved.]
Copyright 2018 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content.
|