Olympics: Tokyo 2020 venues on track for completion, say organizers
Send a link to a friend
[February 12, 2019]
By Jack Tarrant
TOKYO (Reuters) - Tokyo 2020 Olympic
and Paralympic venues remain on track to be completed in time for
test events scheduled for later this year, according to Games
organizers.
Test events for sailing and water polo have already been held but
the main bulk to testing is due to begin this summer, including at
venues purpose built for the Games.
Other than the Olympic Stadium and the Olympic and Paralympic
athletes village, Tokyo Metropolitan Government (TMG) is building
eight new competition venues for the Games.
Many of the events are scheduled to be held at pre-existing venues
in a bid to keep costs down.
During a media venue tour on Tuesday, organizers from the TMG said
construction goals were being met.
"Each arena is preparing for the test events scheduled for around
summer and construction is proceeding smoothly," Tomohiro Terasawa,
venue director for the Ariake Arena, told Reuters.
"We're working hard to ensure everything is on time."
The Ariake Arena, which will host volleyball and wheelchair
basketball, is 51 percent completed as on January 2019, the
organizers informed.
The Tokyo Aquatics Center, which will host swimming and diving, is
also over half completed while the Sea Forest Waterway, due to hold
a rowing test event as early as August, is almost 80 percent
finished.
[to top of second column] |
A general view of the construction site of the Ariake Gymnastics
Centre for Tokyo 2020 Olympic and Paralympic games in Tokyo, Japan
February 12, 2019. REUTERS/Issei Kato
There have been fears over the venue for tennis at the Tokyo 2020
Games, after the contractor hired to renovate parts of the Ariake
Tennis Park went bankrupt in October.
However, the TMG has found a new contractor to work on re-building
17 outdoor courts that should be ready in time for the Olympics.
"For tennis, one part of the construction was delayed," said
Terasawa. "One company's business was doing badly and it went under.
The site reviewed its order and currently a new company is doing the
construction."
The All Japan Tennis Championships, to be held in October, will
serve as the test event for tennis.
Organizers are confident that renovations to the show court at
Ariake, which usually hosts the annual Japan Open, will be ready by
that time with minor delays only impacting the outdoor courts.
(Reporting by Jack Tarrant; editing by Sudipto Ganguly)
[© 2019 Thomson Reuters. All rights
reserved.] Copyright 2019 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content.
|