Exclusive: First big U.S. offshore wind project hits snag due to
fishing-industry concerns
Send a link to a friend
[July 29, 2019]
By Nichola Groom
(Reuters) - Trump administration infighting
is holding up approval of the first major U.S. offshore wind energy
project, with agencies sparring over whether the proposal does enough to
protect the fishing industry, according to interviews and agency
documents.
The delays are a setback to President Donald Trump's efforts to
fast-track big energy infrastructure projects and could threaten the
administration's plans to launch a promising new domestic industry.
How the problem is resolved will shape the regulatory blueprint for a
growing list of offshore wind developers seeking to tap in to rising
U.S. demand for renewable energy, but who face objections from fishermen
worried the turbines will affect commercial species or make fishing more
difficult.
The Trump administration has sought to fire up development of the
nascent offshore wind industry by streamlining permitting and carving
out areas off the coast for leasing - part of its policy to boost
domestic energy production and jobs.
Vineyard Wind, a joint venture between Copenhagen Infrastructure
Partners and Avangrid Inc <AGR.N>, was scheduled to begin construction
this year 14 miles (23 km) off the coast of Massachusetts to power more
than 400,000 homes by 2021 - making it the first large-scale offshore
wind development in the United States.
But a federal environmental study crucial to its permitting has been
repeatedly delayed since April, according to published government
timelines, without any public explanation from Trump administration
officials. Vineyard Wind has said the delays could threaten the
project's viability.
Documents seen by Reuters, which have not previously been made public,
show the National Oceanic and Atmospheric Administration's (NOAA)
National Marine Fisheries Service (NMFS) triggered the delays by
declining to sign off on the project's design, as proposed by the Bureau
of Ocean Energy Management (BOEM), the lead agency on offshore wind
projects.
Under a 2017 Trump executive order aimed at limiting environmental
reviews for major infrastructure projects to two years, federal agencies
must request support from cooperating agencies at three points in the
review process, including before issuing the final environmental impact
study.
Getting the support allows the process to move more quickly, but failing
to get it can force further analysis.
SEEKING AGREEMENT ON FISHING
In an April 16 letter to BOEM, Michael Pentony, regional administrator
for NOAA Fisheries' Greater Atlantic office, said his agency could not
support the environmental permit for Vineyard Wind because the project
failed to fully address the concerns of the fishing industry.
[to top of second column] |
Fish on display in a
fish market at the Fisherman's Wharf in La Libertad, El Salvador,
November 8, 2018. REUTERS/Jose Cabezas
For example, he said, the fishing industry had asked for wider spacing
between turbines than the 0.75 nautical mile laid out in the proposal,
and wanted the turbines aligned in an east-west orientation, rather than
northwest-southeast.
He also said the proposal relied on undefined measures to compensate
fishermen for potential damage to their livelihoods caused by the wind
farm. The issues "require detailed analysis" not currently conducted in
the study.
In a written response to Pentony, seen by Reuters, BOEM Chief
Environmental Officer William Brown said the fishing industry's concerns
"do not rise to the level that would justify the likely extensive
project delays and potential failure of the project."
He added that BOEM could try to issue the environmental permit without
the support of the National Marine Fisheries Service: "We hope that, on
reflection, NMFS will concur with our conclusion. If NMFS does not
concur, however, we are prepared to note its non-concurrence in the
final EIS (environmental impact statement) and the (Record of
Decision)," Brown wrote.
Three months later, the agencies have yet to resolve their differences.
"At this time, we are not yet able to come to a point of concurrence,"
NOAA spokesman John Ewald said in an emailed statement last week.
Because Vineyard Wind is the first such project to undergo the federal
environmental review process, Ewald said NOAA "wants to ensure that
impacts to ocean resources are fully addressed."
BOEM spokesman Stephen Boutwell said NMFS is required to co-sign the
project's Record of Decision, a formal decision document, for the permit
to be issued. The final environmental impact study and record of
decision had originally been expected in April but were later delayed to
June and then early July. Boutwell said the agency does not "have a date
for these publications at this time."
Vineyard Wind said earlier this month that it told federal officials it
would be "very challenging" to move forward with the project in its
current configuration if the environmental permit is not issued within
four to six weeks. The company wants to start construction soon to lock
in a federal tax credit that expires next year. The credit is currently
worth 12% of the value of the project.
NOAA is a division of the U.S. Department of Commerce, while BOEM falls
under the Department of Interior.
(Reporting by Nichola Groom in Los Angeles; Editing by Richard Valdmanis
and Matthew Lewis)
[© 2019 Thomson Reuters. All rights
reserved.] Copyright 2019 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content. |