Logan County Board to vote on
switchyard grading to begin for Sugar Creek Wind Farm
Send a link to a friend
[May 21, 2019]
On Thursday, May 16, the Logan County Board held its Board Workshop
to hear committee updates and discuss motions that will be voted on
at next Tuesday’s Regular Board. One focus of discussion was a
request from Liberty Power on behalf of the Sugar Creek Wind Farm.
Kyle Barry, attorney for the project, said by July 1, the project
must turn over ground to Ameren so Ameren can build the switchyard,
which provides the point of interconnection with the electric grid.
Before the ground can be turned over to Ameren certain activities
must be completed. The company needs to bring in dirt and level it
out so Ameren can do their work. Barry asked whether certain
approvals are necessary before the work can be done.
It will take several weeks to bring in the dirt and Barry said if it
is not done by July 1, Ameren will not be able to meet its deadline
and it will delay the start of construction.
The wind ordinance found in Appendix E of the zoning code says no
wind farm can be constructed, erected, installed, or located within
Logan County until it meets prior siting approval, and Barry asked
whether the activities related to grading involve construction or
installation activities. Federal regulations by the U.S. EPA defines
construction as a physical change or change in the method of
operation of a building including fabrication, erection,
installation, and demolition.
The bottom line is preparatory work like grading is not considered
construction under federal regulation and Barry said the county
ordinance imposes standards stricter than what the EPA imposes.
If you look at the switchyard, it will eventually be owned and
operated by Ameren because it will part of the electric grid, and
Barry said if not for the wind farm Ameren would not need the
approval.
The board already essentially distinguished between preparatory work
and construction work when it approved the road use agreement for
the project. Barry said the road use agreement defines preparatory
work and construction activities differently. Barry was in McDonough
County last night, and said Ameren was able to begin work on the
switchyard for that project without having the final permit in
place.
Liberty Power’s Yuri Aratov, project manager for the Sugar Creek
Wind Farm project, said the arrangement with Ameren is that the road
must be graded by July 1. Ameren has a no outage period between May
and September, which creates a problem for Liberty Power. If not
turned over by July 1, it could push the April 30 date for beginning
construction to September or October 2020.
Ameren’s Engineering team is already backed up with work on solar
projects, so Stan Komperda said any time delays would be of concern.
Scott Schaffenacker, Vice chairman of the board, asked if the work
would interfere with the road use agreement.
Logan County Highway Engineer Bret Aukamp said the road use
agreement is for use of public roads and the location of the
substation is adjacent to Route 10. They would be accessing the area
from the state route and the construction could take place without
affecting any of the local roads.
Schaffenacker said it seems like dirt work could be done without the
full permit in place and asked whether the board needed to act.
Logan County Zoning Officer Will D’Andrea said the only reason
grading would be going on is to prepare for a substation that is
only there because of the project, and the substation is just
allowed under conditional use.
[to top of second column] |
Ameren got approval previously for land use for the Fogerty substation. He will
not issue a permit to start any construction until every condition is satisfied.
D’Andrea asked how much dirt work would be needed since the dirt work is to
prepare for some construction of a substation.
Board member Chuck Ruben said the board can authorize them to do the work but
must set up some conditions such as having an access road off the highway with
the state of Illinois and some kind of decommissioning bond to put the road back
into its original shape.
Aratov said they already have the Letter of Credit for the Decommissioning
Agreement and are expecting a permit from the Illinois Department of
Transportation. They would not start any work until that permit is in place.
Brett Skaggs, business manager the Operating Engineers of Springfield, said they
represent about 1,300 members and these people go through a lot of hours and
time to put roads back the way they were.
Ruben asked if the letter of credit would satisfy the agreement.
Since he has not seen the plans for what grading and road work would take place,
Aukamp said he cannot answer that question yet.
Aratov said the letter of credit is more than double the cost being paid to
their contractor for the work.
To verify that, Aukamp will need to see plans for what will be done at the
worksite.
Logan County State’s Attorney Brad Hauge said the board has the authority to
decide whether to grant or not grant what Liberty Power is asking, and it is
covered legally either way. Hauge has also talked to Barry, D’Andrea and Aukamp
about the issue.
Though D’Andrea had pointed out grading for a rock quarry or digging for a
basement would not be allowed, Hauge said what they are asking is different
since it is for a wind farm and it is a company the county has worked with in
the past. Liberty Power has complied with several conditions on the conditional
use permit and are working toward the rest, so Hauge said he believes all the
conditions should be in place by mid-summer.
Aukamp said he does not have a deadline, but they are making progress and road
construction may begin later in the summer.
Barry said July 1 is a functional deadline since that is when Ameren needs to
start construction.
Hauge said if the board were to approve the grading, that gives the company an
added incentive to finish it up on time, have costs up front, and be invested
financially in the project, which may encourage Liberty Power to complete the
agreements.
Board member David Hepler said that on Tuesday he would motion to approve the
initial grading as requested by Liberty Power.
Ruben said he would amend the motion to delineate conditions such as providing
Aukamp with plans showing the letter of credit far exceeds the value of what is
being put in and that Aukamp has time to look at it before the approval is
granted.
The board will vote on whether to approve the work at Tuesday’s meeting.
[Angela Reiners] |