Bombardier declines comment on Swiss train deal
profitability
Send a link to a friend
[May 29, 2019]
By John Miller
ZURICH (Reuters) - Bombardier delivered
three double-decker trains to Switzerland this month for a total of 15,
it said on Wednesday, but declined to comment after the Swiss rail boss
said the company was losing money on the overdue contract.
Faulty doors, software and questions over ride comfort on the first
trains to be delivered have complicated the 2010 deal, which is about
five years behind schedule. Switzerland's largest-ever trains contract
now calls for most of the 62 trains on order to be delivered by the end
of 2020.
"For Bombardier, the FV Dosto (double-decker) trains are ...a
loss-making business deal," Swiss Federal Railways (SBB) Chief Executive
Andreas Meyer told the Neue Zuercher Zeitung (NZZ) newspaper in an
interview published on Wednesday.
"Bombardier will try to minimise these losses. But the contractual
requirements are relatively clear and comfortable for us."
Without giving specifics, Meyer said the contract provided for financial
penalties against Bombardier for not living up to its obligations.
Bombardier has cut its forecast for profit and revenue as its railcar
unit struggles, but said on Wednesday it would not break out how
problems with the Swiss order might contribute to that.
"We do not comment on the profitability of our projects,” a Bombardier
spokesman said. "The FV-Dosto is a unique high-tech product tailored to
the needs of Switzerland. The development of a new product is naturally
associated with high investment costs."
[to top of second column] |
The Bombardier FV-Dosto double-deck train "Ville de Geneve" of Swiss
railway operator SBB is seen at the central station in Zurich,
Switzerland April 29, 2019. REUTERS/Arnd Wiegmann/File Photo
SBB and Bombardier said on May 1 that the problems with the first 12 trains were
being ironed out.
"We are making rapid and strong progress," the Bombardier spokesman said on
Wednesday.
Meyer conceded that SBB was responsible for one year of the delays due to
changing requirements, but said Bombardier was to blame for the remainder, as
well as the time taken to fix problems that have plagued the initial 12
deliveries.
Meyer predicted a potential disagreement over which side is responsible for what
share of the damages. "The conflict will come," he said.
Bombardier said it was committed to working out any disputes. "We are confident
that we will find constructive solutions with SBB on all aspects in the
foreseeable future," its spokesman said.
(Reporting by John Miller; editing by Mark Potter and Jason Neely)
[© 2019 Thomson Reuters. All rights
reserved.] Copyright 2019 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content.
|