Trump's fast-tracking of oil pipelines hits legal roadblocks
Send a link to a friend
[October 09, 2019] By
Scott DiSavino and Stephanie Kelly
NEW YORK (Reuters) - The Trump
administration's effort to cut red tape and speed up major energy
projects has backfired in the case of the three biggest U.S. pipelines
now planned or under construction.
All three have been stalled by successful legal challenges by
environmental groups alleging the administration failed to apply the
regulatory scrutiny required under the law.
The Republican administration tried to accelerate permits for two
multi-billion-dollar natural gas lines and jumpstart the long-stalled
Keystone XL crude oil pipeline that would start in Canada. Judges halted
construction on all three over the past two years, ruling that the
administration granted permits without conducting adequate studies or
providing enough alternatives to protect endangered species or national
forests.
The delays have caused the two giant gas pipelines - Dominion Energy
Inc's Atlantic Coast and EQM Midstream Partners LP's Mountain Valley -
to increase their cost estimates by hundreds of millions of dollars,
according to the companies. The Atlantic Coast pipeline may never be
completed unless the U.S. Supreme Court overturns a lower-court decision
blocking its planned route, analysts said.
Lawsuits alleging regulatory lapses are not new, but they were
unsuccessful during the administration of Trump's predecessor, Democrat
Barack Obama. Plaintiffs lost five separate lawsuits alleging regulatory
failures during Obama's administration, according to a Reuters review of
court filings for major interstate gas pipes built since 2010.
"Environmental groups definitely have been going after these pipelines
more aggressively," said Amy Vazquez, Houston-based partner at the law
firm of Jones Walker, who specializes in energy litigation. "It's
probably because they're having a fair bit of success."
The White House declined to comment. An Energy Department spokeswoman
did not comment on the litigation but said the administration remains
committed to streamlining energy infrastructure development.
D.J. Gerken, senior attorney with the Southern Environmental Law Center
in Asheville, North Carolina, represented the Sierra Club and other
environmental groups in cases challenging the Atlantic Coast pipeline.
He said the administration's rush to help industry move faster invited
the legal challenges.
"Pressure from the utilities that stand to benefit from this project and
the Trump administration produced flawed permits," he said.
'MYSTERIOUS' REGULATORY REVERSAL
In the case of Dominion's 600-mile (966-km) Atlantic Coast gas pipeline,
from West Virginia to North Carolina, the U.S. Forest Service originally
expressed skepticism about the project in 2016 when Obama was president,
requesting alternative designs. But after Trump took office, the Forest
Service changed course, and issued permits and a waiver for the line to
cross the Appalachian Trail on national forestland in Virginia.
Petitioners including the Sierra Club, an environmental advocacy
organization, sued the Forest Service, alleging the agency violated
three federal acts in issuing a construction permit.
In December 2018, the U.S. Fourth Circuit Court of Appeals vacated the
Forest Service decisions, with Judge Stephanie Thacker noting in her
ruling that "the Forest Service's serious environmental concerns that
were suddenly, and mysteriously, assuaged in time to meet a private
pipeline company's deadlines."
The court said the Forest Service lacked authority to allow Dominion to
build across the Appalachian Trail, which is administered by the
Department of Interior. The Forest Service declined to comment.
In July, in another Atlantic Coast case brought by groups including the
Sierra Club and Defenders of Wildlife, the Fourth Circuit vacated a U.S.
Fish and Wildlife Service permit. Chief Judge Roger Gregory ruled that
the agency, in "fast-tracking" decisions, lost sight of its mandate to
protect threatened species.
[to top of second column] |
A warning sign for the Mountain Valley Pipeline in front of
a home near Elliston, Virginia, U.S. September 30, 2019.
Picture taken September 30, 2019. REUTERS/Charles Mostoller
The U.S. Fish and Wildlife Service declined to comment.
Atlantic Coast's original cost estimate of $6 billion to $6.5 billion has risen
to $7 billion to $7.5 billion, the company said. The projected completion has
shifted from late 2019 to late 2021.
The U.S. Supreme Court in October agreed to hear the Appalachian Trail case and
could overrule the decision halting construction across that route.
Dominion has stopped construction on the pipe since December 2018. Spokesman
Aaron Ruby said the company is confident the high court will rule in its favor
and "uphold the longstanding precedent allowing pipeline crossings of the
Appalachian Trail.”
RISING COSTS, LEGAL RISKS
The Fourth Circuit appeals court also stopped work on EQM’s 303-mile (488-km)
Mountain Valley gas pipe from West Virginia to Virginia in June 2018, agreeing
with the Sierra Club and other plaintiffs that permits issued by the Army Corps
violated West Virginia rules related to stream crossings.
The state has since altered its rules, and the U.S. Army Corps of Engineers is
in the process of issuing new permits for this pipeline and Atlantic Coast. But
the Sierra Club is still challenging a Fish and Wildlife Service permit in a
case that also is being heard by the Fourth Circuit.
EQM originally expected to complete Mountain Valley by the end of 2018 at a cost
of $3.5 billion. The company said publicly that it expected the pipeline, which
is mostly complete, will cost up to $5 billion and enter service in mid-2020.
Diana Charletta, chief operating officer at EQM, said that recent court
decisions "have brought uncertainty and a high-level of scrutiny to the
agencies’ decisions."
Officials at both Dominion and EQM dispute that approvals were fast-tracked.
Dominion pointed out that it filed its application to build Atlantic Coast in
2014.
"I don't think any person can look at the regulatory review process for Atlantic
Coast pipeline and say that it was fast-tracked," said Ruby, the Dominion
spokesman.
EFFORT TO REVIVE KEYSTONE STALLS
TC Energy Corp's $8 billion Keystone XL pipeline, originally blocked by Obama in
2015, was revived by Trump in 2017 with the issuance of a presidential permit
for the line, which would ship crude from Canada to the U.S. Gulf Coast.
Federal Judge Brian Morris in Montana blocked work on the pipe in November 2018,
citing a lack of due diligence by federal regulators regarding greenhouse gas
emissions and Native American land rights.
The Trump administration tried to circumvent that ruling by rescinding its
original presidential permit and issuing a new one in March. That second permit
now faces legal challenges from Native American groups.
TC Energy said it continues to monitor U.S. legal and regulatory issues while it
plans construction. “We are committed to Keystone XL as it remains an important
project for our company and for North America,” said Terry Cunha, spokesman for
TC Energy.
Canadian producer Suncor Energy said in early September that the uncertain U.S.
political landscape makes it unclear that the pipeline will be built. "That's
one a lot of people are doing soul-searching about right now," said Suncor CEO
Mark Little.
(Reporting by Scott DiSavino and Stephanie Kelly; Editing by David Gaffen and
Brian Thevenot)
[© 2019 Thomson Reuters. All rights
reserved.] Copyright 2019 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content. |