Trump's fast-tracking of oil pipelines hits legal roadblocks
Send a link to a friend
[October 09, 2019]
By Scott DiSavino and Stephanie Kelly
NEW YORK (Reuters) - The Trump
administration's effort to cut red tape and speed up major energy
projects has backfired in the case of the three biggest U.S. pipelines
now planned or under construction.
All three have been stalled by successful legal challenges by
environmental groups alleging the administration failed to apply the
regulatory scrutiny required under the law.
The Republican administration tried to accelerate permits for two
multi-billion-dollar natural gas lines and jumpstart the long-stalled
Keystone XL crude oil pipeline that would start in Canada. Judges halted
construction on all three over the past two years, ruling that the
administration granted permits without conducting adequate studies or
providing enough alternatives to protect endangered species or national
forests.
The delays have caused the two giant gas pipelines - Dominion Energy
Inc's Atlantic Coast and EQM Midstream Partners LP's Mountain Valley -
to increase their cost estimates by hundreds of millions of dollars,
according to the companies. The Atlantic Coast pipeline may never be
completed unless the U.S. Supreme Court overturns a lower-court decision
blocking its planned route, analysts said.
Lawsuits alleging regulatory lapses are not new, but they were
unsuccessful during the administration of Trump's predecessor, Democrat
Barack Obama. Plaintiffs lost five separate lawsuits alleging regulatory
failures during Obama's administration, according to a Reuters review of
court filings for major interstate gas pipes built since 2010.
"Environmental groups definitely have been going after these pipelines
more aggressively," said Amy Vazquez, Houston-based partner at the law
firm of Jones Walker, who specializes in energy litigation. "It's
probably because they're having a fair bit of success."
The White House declined to comment. An Energy Department spokeswoman
did not comment on the litigation but said the administration remains
committed to streamlining energy infrastructure development.
D.J. Gerken, senior attorney with the Southern Environmental Law Center
in Asheville, North Carolina, represented the Sierra Club and other
environmental groups in cases challenging the Atlantic Coast pipeline.
He said the administration's rush to help industry move faster invited
the legal challenges.
"Pressure from the utilities that stand to benefit from this project and
the Trump administration produced flawed permits," he said.
'MYSTERIOUS' REGULATORY REVERSAL
In the case of Dominion's 600-mile (966-km) Atlantic Coast gas pipeline,
from West Virginia to North Carolina, the U.S. Forest Service originally
expressed skepticism about the project in 2016 when Obama was president,
requesting alternative designs. But after Trump took office, the Forest
Service changed course, and issued permits and a waiver for the line to
cross the Appalachian Trail on national forestland in Virginia.
Petitioners including the Sierra Club, an environmental advocacy
organization, sued the Forest Service, alleging the agency violated
three federal acts in issuing a construction permit.
In December 2018, the U.S. Fourth Circuit Court of Appeals vacated the
Forest Service decisions, with Judge Stephanie Thacker noting in her
ruling that "the Forest Service's serious environmental concerns that
were suddenly, and mysteriously, assuaged in time to meet a private
pipeline company's deadlines."
The court said the Forest Service lacked authority to allow Dominion to
build across the Appalachian Trail, which is administered by the
Department of Interior. The Forest Service declined to comment.
In July, in another Atlantic Coast case brought by groups including the
Sierra Club and Defenders of Wildlife, the Fourth Circuit vacated a U.S.
Fish and Wildlife Service permit. Chief Judge Roger Gregory ruled that
the agency, in "fast-tracking" decisions, lost sight of its mandate to
protect threatened species.
[to top of second column]
|
An unburied section of the under-construction Mountain Valley
Pipeline near Elliston, Virginia, U.S. September 30, 2019.
REUTERS/Charles Mostoller
The U.S. Fish and Wildlife Service declined to comment.
Atlantic Coast's original cost estimate of $6 billion to $6.5
billion has risen to $7 billion to $7.5 billion, the company said.
The projected completion has shifted from late 2019 to late 2021.
The U.S. Supreme Court in October agreed to hear the Appalachian
Trail case and could overrule the decision halting construction
across that route.
Dominion has stopped construction on the pipe since December 2018.
Spokesman Aaron Ruby said the company is confident the high court
will rule in its favor and "uphold the longstanding precedent
allowing pipeline crossings of the Appalachian Trail.”
RISING COSTS, LEGAL RISKS
The Fourth Circuit appeals court also stopped work on EQM’s 303-mile
(488-km) Mountain Valley gas pipe from West Virginia to Virginia in
June 2018, agreeing with the Sierra Club and other plaintiffs that
permits issued by the Army Corps violated West Virginia rules
related to stream crossings.
The state has since altered its rules, and the U.S. Army Corps of
Engineers is in the process of issuing new permits for this pipeline
and Atlantic Coast. But the Sierra Club is still challenging a Fish
and Wildlife Service permit in a case that also is being heard by
the Fourth Circuit.
EQM originally expected to complete Mountain Valley by the end of
2018 at a cost of $3.5 billion. The company said publicly that it
expected the pipeline, which is mostly complete, will cost up to $5
billion and enter service in mid-2020.
Diana Charletta, chief operating officer at EQM, said that recent
court decisions "have brought uncertainty and a high-level of
scrutiny to the agencies’ decisions."
Officials at both Dominion and EQM dispute that approvals were
fast-tracked. Dominion pointed out that it filed its application to
build Atlantic Coast in 2014.
"I don't think any person can look at the regulatory review process
for Atlantic Coast pipeline and say that it was fast-tracked," said
Ruby, the Dominion spokesman.
EFFORT TO REVIVE KEYSTONE STALLS
TC Energy Corp's $8 billion Keystone XL pipeline, originally blocked
by Obama in 2015, was revived by Trump in 2017 with the issuance of
a presidential permit for the line, which would ship crude from
Canada to the U.S. Gulf Coast.
Federal Judge Brian Morris in Montana blocked work on the pipe in
November 2018, citing a lack of due diligence by federal regulators
regarding greenhouse gas emissions and Native American land rights.
The Trump administration tried to circumvent that ruling by
rescinding its original presidential permit and issuing a new one in
March. That second permit now faces legal challenges from Native
American groups.
TC Energy said it continues to monitor U.S. legal and regulatory
issues while it plans construction. “We are committed to Keystone XL
as it remains an important project for our company and for North
America,” said Terry Cunha, spokesman for TC Energy.
Canadian producer Suncor Energy said in early September that the
uncertain U.S. political landscape makes it unclear that the
pipeline will be built. "That's one a lot of people are doing
soul-searching about right now," said Suncor CEO Mark Little.
(Reporting by Scott DiSavino and Stephanie Kelly; Editing by David
Gaffen and Brian Thevenot)
[© 2019 Thomson Reuters. All rights
reserved.]
Copyright 2019 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content. |