Scarification and Oil & Chip projects begin Monday in Lincoln

Send a link to a friend  Share

[August 26, 2020] 

The 2020 City of Lincoln Scarification and Oil and chip project will get underway beginning Monday, August 24, 2020. Please be on the lookout for temporary no parking signs in your area and please do not park in the areas posted with these signs.

List of streets scheduled for work - pdf

The contractor will start with the streets that are going to be scarified, once this is complete the street will be regraded and compacted. These streets will not be resurfaced immediately, so residents should avoid driving on them if at all possible. If they do, we recommend not exceeding 10 mph on these streets.

A primer oil will be applied 18 to 24 hours before these streets are resurfaced and we highly recommend residents do not drive on these areas unless absolutely necessary. If it is unavoidable, we recommend not exceeding 5 mph.

It would be very likely that oil will transfer from tires to the vehicle and it may also track onto other surfaces such as driveways and sidewalks. A base coat of rock will be applied and then a second surface coat will be applied to these streets and the other streets just receiving a standard oil and chip.

[to top of second column]

These are weather sensitive operations so any rain could change the schedule.

Streets will remain open unless crews are actively working.

If anyone decides to drive on this oil, they do so at their own risk. The City or contractors will not be responsible for any damage caused by doing so. As always it is recommended that motorists and pedestrians alike avoid these areas if possible. If you must travel in these areas, please use extreme caution.



Any questions or concerns, please contact the City of Lincoln Street Department at 217-732-4655.

[Walt Landers
Street Superintendent
City of Lincoln]