Vietnam faces the risk of severe power shortages from 2021 as
demand outpaces construction of new plants.
The project in Thua Thien Hue province will include a 4-gigawatt
power plant, an LNG terminal and storage facilities, John
Rockhold told Reuters on the sidelines of the Vietnam Energy
Summit.
Construction of the power plant is scheduled to begin next year,
so that the first phase of 2.4 GW will be operational from 2024
and the entire plant from 2027, Rockhold said.
"We have big support from the U.S. government for the project,
as they have LNG to sell," he said. "We have a number of U.S.
LNG suppliers and we are doing the shopping right now."
When fully operational, the project will import around $1.2
billion worth of U.S. LNG a year, he said, adding it would help
narrow the trade deficit the U.S. has incurred with Vietnam.
Vietnam has been seeking to import more U.S. goods, such as coal
and LNG, to narrow the trade gap after President Donald Trump
threatened tariffs on its products amid the Chinese-U.S. trade
war.
Chan May LNG, which is 60% owned by U.S. investors and 40% by
Vietnamese investors, said a number of institutions had shown
interest in financing the projects, including U.S. Exim Bank,
the U.S. International Development Finance Corp. and the
International Finance Corp.
Rockhold said the plant will use turbines from General Electric.
"The project is now on the table of the Prime Minister (of
Vietnam) and we hope to receive an investment licence this
fall," he said.
(Reporting by Khanh Vu; Editing by Ed Davies)
[© 2020 Thomson Reuters. All rights
reserved.] Copyright 2020 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content.
|
|