Solar applicants question need for
road use agreement
Send a link to a friend
[June 16, 2020]
At the Logan County Board Workshop on Thursday, June 11, one focus
of discussion was the Mulligan Solar Project.
Board members present were Dave Blankenship, Emily Davenport, Janet
Estill, Bob Farmer, David Hepler, Steve Jenness, Chuck Ruben, Bob
Sanders, Scott Schaffenacker, Jim Wessbecher and Annette Welch.
Cameron Halpin was absent.
On Tuesday, June 16, Planning and Zoning Committee Chairman David
Hepler will bring forward a motion for a conditional use permit for
the Mulligan Solar Project.
Project Manager Erin Baker of Apex handed out materials to the board
members. Baker said, Mulligan Solar’s application is for an energy
system that would generate up to 70 megawatts from parcels set on
874 acres.
The project would interconnect to the existing Ameren Fogarty
substation, located northeast of the town of Broadwell.
Interconnection facilities or the “Project Substation” will be
located on an adjacent parcel.
The Project is roughly bounded by 1300th Street to the north, Salt
Creek to the east, 1100th street to the south, and 800th Avenue to
the west within the boundaries of Broadwell Township.
Baker said though participants have signed solar leases for 874
aces, not all the area will be covered by panels. Some of the
acreage is for setbacks for roads, houses and other infrastructure.
Right now, Apex and Mulligan Solar are completing interconnection
studies and executing an interconnection agreement with Ameren.
Early next year, Baker said, the interconnection agreement would be
executed. Then they will start applying for building permits with
hopes to start construction in spring or fall 2021. Baker said they
hope to operational by the end of next year.
Project attorney Kyle Barry attended prior meetings on Wednesday,
June 3 and Thursday, June 4 with the Regional Planning Commission,
who voted 7-0, and the Zoning Board of Appeals, who voted 5-1, to
recommend approval of the conditional use permit.
The conditional use request has 21 conditions that need to be met
for the project. Barry said almost 90 percent of the conditions are
in good shape, but two took the company by surprise, which relate to
road plans and road use agreements.
The specific conditions Barry is referring to include:
Condition 16: Submission of signed and recorded copies
of all Road Use Agreements, if applicable.
Condition 17: Receipt of township road commissioner and
county engineer approval of roadway plans for all affected roadways,
along with appropriate easements from property owners where the
roadway improvements will occur outside of the existing public
right-of-way, if applicable.
However, the solar ordinance adopted by the board does not include a
road use agreement requirement, which Barry said is typical.
Unlike wind projects, Barry said solar projects do not require big
cranes or heavy equipment to bring in loads. With a couple
exceptions, Barry said, equipment can be supplied to the site using
legal loads, so impacts on the road would be the same as from a
grain truck.
According to state statutes, Barry said conditions must be
reasonably necessary to meet the standards. Barry said the solar
ordinance does not create any standards for road use agreements.
Barry also looked at section 10.3 (on conditional use) of the zoning
ordinance, and said it does not include any references to road use
agreement or roads.
The conditional use section does include indirect references to
traffic and ingress, but Barry said these references are about the
site and traffic in the neighborhood.
That raised some concerns, so Barry spoke to Logan County State’s
Attorney Brad Hauge about it. Barry said, as written the provisions
in those two conditions create uncertainty about road use
agreements, especially since they say, “if applicable.” Barry and
the project developers are not sure what that means or what road use
agreement will be required.
It does not appear the project will impact any county roads, so
Barry said it is not clear why conditions relating to the road would
be imposed by the county. Traffic will come directly off the
interstate and just impact a few miles of township roads.
After the feedback he received from Hauge, Barry said he is
proposing some amended language to provide more certainty. Barry
said it would also involve a study of the roads by a third-party
engineer to determine whether a road use agreement would be
necessary.
[to top of second column] |
If the third-party engineer determines a road use agreement would be necessary
after doing a baseline survey, Barry said, the applicant would have no problem
entering into a road use agreement.
There was another area Barry wanted to propose a language change. He wants to
amend the time for activity on the project, limiting it to 6 a.m. to 6 p.m.
instead of sunrise to sunset. Barry said that would take away any uncertainty
about whether it is actually light or dark.
In the event of extenuating circumstances, the applicants could make a written
request to the zoning officer. The zoning officer could then use his discretion
in deciding whether some nighttime activities could take place.
Hauge asked Logan County Zoning Officer Will D’Andrea to explain why the
original conditions were put in place and his thought on these amendments.
D’Andrea said Barry is right, that there is no specific language about a road
use agreement being required as part of the Solar Farm Ordinance. However,
D’Andrea said, part of the general approval criteria for conditional use
provides for roads and utilities.
At this point, D’Andrea said, there has not been much discussion about road
impacts with the Broadwell Township Road Commissioner. Therefore, D’Andrea said
the conditions will require the township road commissioner’s discretion as to
whether a road use agreement is required.
D’Andrea is not sure what the impact on the roads might be during the
construction. Though, those bringing in loads would not be using a county road,
D’Andrea said, most of the roads impacted by the wind farms were not county
roads either.
Without a road use agreement, D’Andrea said, if there is damage there is a
question of who is responsible for maintaining and fixing the roads. Is it the
taxpayer or the township?
Hauge asked whether the clause ‘if applicable’ in condition 17 was based on a
lack of information presented at the ZBA hearing.
D’Andrea said the township road commissioner had not been contacted yet about
the impacts or the level of construction activity. Therefore, D’Andrea said the
township commissioner is a bit concerned.
As far as times, D’Andrea said, it is fine to further limit construction from 6
a.m. to 6 p.m.
In the future, Vice chairman Schaffenacker asked that when the applicants send
out certified letters, one be sent to the township office.
D’Andrea said Mr. Barry did send a letter to the township office.
Hauge agrees with having extra protection for the township.
Some of the board members felt it would be prudent to have provisions in place
for the roads.
Sanders agreed there should be protection whether it is a road use agreement or
something similar. He said people do not intend to damage the road, but it
happens.
Ruben said he would think they [the developers] would want to get a hold of the
township commissioner and get something in place because of situations that we
have seen [with other roads]. The township commission can suddenly decide to
shut a road down and not have to answer to anybody. Ruben said having these
agreements is in their [the builders] best interests.
Wessbecher wants the protections in place since drivers do not always follow the
exact route.
Though we do not know as much about solar, Welch said her concern is about
something happening and not having any road use agreement. She would rather have
some sort of agreement even if they determine no repairs are expected.
Hepler said he would make amendments Tuesday for the recommended time changes
and for the road use agreement after consulting a third party.
Chairman Davenport asked whether the company requires a third-party
consultation.
Hepler said it sounds like they could mandate it.
Though a third-party engineer is consulted for review, D’Andrea said they should
not be the ones to decide on road use agreements necessary. That should be the
township road commissioner.
The board will vote on the motion at their Regular Board meeting tonight,
Tuesday, June 16 at 6 p.m on the second floor of the Orr Building.
[Angela Reiners] |