U.S. appeals court denies Dakota Access rehearing request, environmental
review to continue
Send a link to a friend
[April 24, 2021]
By Laila Kearney and Devika Krishna Kumar
NEW YORK (Reuters) - A U.S. appeals court
on Friday denied Dakota Access LLC's petition for a rehearing of a court
decision that canceled a key permit for its oil pipeline and ordered an
environmental review, court documents show.
The decision by the United States Court of Appeals for the District of
Columbia means the Dakota Access Pipeline (DAPL) technically is still
trespassing on federal land because it does not have a permit to cross
under the Dakotas' Lake Oahe. The line is currently operating
indefinitely but will be reassessed once the environmental review of the
line is completed in March 2022.
The 570,000 barrel-per-day DAPL began operating in mid-2017 but drew
controversy during construction as Native American tribes and activists
protested its route under Oahe, a critical drinking water source for the
tribes.
Last summer, a U.S. district court judge threw out a federal permit for
the line to operate under the lake and ordered an environmental review
for that section of the pipeline. A three-judge panel at the circuit
court in January upheld the lower court's decision to vacate the permit
and require the review.
The pipeline's operators wanted the circuit court to reconsider the
panel's decision, but the court unanimously denied the request. The
decision leaves only the U.S. Supreme Court for Dakota Access to oppose
the environmental review and permit denial, but it's not certain the
nation's highest court will take up the case.
[to top of second column]
|
Law enforcement officers move into the main opposition camp against
the Dakota Access oil pipeline near Cannon Ball, North Dakota, U.S.,
February 23, 2017. REUTERS/Terray Sylvester
"This is a pretty definitive statement that the legal
issues in this case do not warrant attention from the Supreme
Court," said Earthjustice attorney Jan Hasselman, who represents the
Standing Rock Sioux in the case. "Here, not only didn't we see
dissents, not a single judge called for a vote."
A spokeswoman for Energy Transfer LP, DAPL's majority owner,
declined to comment on current or pending legal matters.
DAPL is the largest pipeline out of the Bakken region, which
produces about 1 million barrels of crude per day in North Dakota
and Montana. If the pipeline were forced to close, the state of
North Dakota estimates production could fall by 400,000 bpd
temporarily.
Once the U.S. Army Corps of Engineers completes its environmental
review, a decision will be made on whether to issue a new permit for
the pipeline.
On Friday, the Native American tribes that brought the lawsuit
argued to the District Court that Dakota Access pipeline's operators
exaggerated the economic impact from shutting down the pipeline and
the pipeline’s safety has never been evaluated as the law requires.
(Reporting by Laila Kearney and Devika Krishna Kumar; Editing by Dan
Grebler and Aurora Ellis)
[© 2021 Thomson Reuters. All rights
reserved.] Copyright 2021 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content. |