A portion of the Logan County
Courthouse restoration budget rejected for high costs
Send a link to a friend
[February 22, 2021]
At the Logan County Board Workshop on Thursday, February 11, the
board heard updates from several committees. One focus of discussion
was the courthouse restoration project.
On Tuesday, Building and Grounds Chairman David Blankenship would
motion for approval of an updated budget for the scope of work.
The initial budget proposed by CTS was rejected by the Construction
Technical Committee due to the high costs. Bill Walter of MRTS will
take over that scope of work and projected bidding at a greatly
reduced cost. Blankenship reminded the board it is a projected
budget with just baseline specifications right now. The final budget
and specifications will be much more detailed.
Though the budget is just a projected one, Walter said it would at
least get him into the ballpark for costs. He will be working on
developing the specifications for the bid documents and that will
generate the exact costs for these items.
Another motion Blankenship would bring forward is for shifting of
the dome and construction management from CTS to MRTS.
This recommendation has come from the Construction Technical
Committee because MRTS has more experience than CTS in this area.
Blankenship said he is more comfortable with MRTS overseeing the
contractors. CTS would still oversee the performance contract side
related to HVAC and energy savings.
Construction Technical Committee member George Mencken explained the
issue further. Mencken said the presentation from CTS had some
estimated costs for some of the work that was way too high, up to 15
times higher than actual costs.
Though Mencken said it can be hard to project costs for materials,
all the costs projected by CTS were tremendously high. In one
instance, for moving the bell from the roof to the ground, CTS
projected costs at $22,000. Mencken said a crane could be rented for
approximately $1,000 with the actual work being completed in less
than a day.
Mencken said CTS did not show who they went through to get bids or
how many bids they got. Walter was able to get his own estimates and
specs at a significant cost savings. Walter’s projected costs were
substantially less than what CTS projected.
In Mencken’s experience, it is hard to trust somebody coming in with
bids that high. He would also have trouble trusting the quality
control.
Board member Bob Sanders asked what CTS would still be managing.
If the board adopts the motion CTS would be responsible for the
design work excluding the dome, the energy performance contract and
the construction management oversight of the energy performance
contract. Blankenship said the responsibility that would be
transferred over from CTS to MRTS is just a small portion.
[to top of second column] |
The individuals from CTS have strong architectural and engineering backgrounds
and Walter said they are sharp individuals. The higher costs CTS projected may
have been to cover liability.
CTS is more than capable of developing the specifications. These specifications
will be overseen by the Tech Committee and Walter, who will see that they
conform with the plans. Walter would be commenting on and editing these
documents, then bring them to the Tech Committee before the documents go to the
board for approval.
Blankenship said CTS does phenomenal design work, which is why CTS would still
be responsible for the design and the performance contract. He just feels the
construction management side will be much better handled by Walter with his
years of experience. The board will vote Tuesday on whether to approve the
motions regarding the performance contract and construction management design.
The board would also be voting on a motion to expend $330,607 for scaffolding
shoring / bracing. In doing oversight work, Blankenship said Mr. Walter
discovered additional support is needed on the roof for the dome scaffolding.
Though it may sound like this cost will be going over budget, Blankenship said
most, if not all, costs would be offset. Mr. Walter agreed the cost would likely
be offset. The dome repair is now estimated at $2.2 M, which is lower than the
original estimate of $3.5 M. Initial costs for the bracing were estimated at
over $659,097. Through four or five redesigns, Blankenship said the cost is down
to $330,607. They may be able to sell the steel to offset costs.
During review of the scaffolding shoring base support design, Walter said loose
I beams were discovered in the attic. When Walter investigated the proposed
design further, he determined the load bearing characteristics in one fourth of
the work area were not adequate. New base shoring beams have been incorporated
into the designed to compensate for the insufficiencies and make everything
safer from a structural standpoint and for personnel.
Board Vice Chairman Scott Schaffenacker asked about selling the beams and
whether that is in the scope of work.
Walter will work with contacts in the steel industry and said it should be easy
to sell the beams. Steel is at a premium right now and a price can be
negotiated.
The board would vote on these motions at their Regular meeting which due to
weather was postponed from Feb. 16 to Tuesday, Feb. 23.
[Angela Reiners] |