Australian documents showed French submarine project was at risk for
years
Send a link to a friend
[September 21, 2021]
By Kirsty Needham
SYDNEY (Reuters) - France shouldn't have
been surprised that Australia cancelled a submarine contract, as major
concerns about delays, cost overruns and suitability had been aired
officially and publicly for years, Australian politicians said.
Paris has recalled its ambassadors from Canberra and Washington, saying
it was blindsided by Canberra's decision to build nuclear-powered
submarines with the U.S. and Britain rather than stick with its contract
for French diesel submarines.
Yet as early as September 2018, an independent oversight board led by a
former U.S. Secretary of the Navy Donald Winter had advised Australia to
look at alternatives to the French submarine, and questioned whether the
project was in the national interest, a 2020 public report from the
country's Auditor-General shows.
Australian parliamentary hearings and reports on the project, first
priced at $40 billion and more recently at $60 billion, even before
construction had begun, also showed problems emerging. In June the
defence secretary told parliament "contingency planning" for the
programme was under way.
"They would have to have their eyes shut not to realise the danger they
were facing," said Rex Patrick, an independent senator for South
Australia, referring to France.
Government ministers said this week Canberra had been "up front" with
Paris about the problems.
A French lawmaker also raised questions in the country's parliament in
June about Australian concerns over delays, and whether Australia might
be considering submarine alternatives, French government records show.
"We chose not to go through a gate in a contract," Prime Minister Scott
Morrison told reporters when he arrived in New York on Monday. "The
contract was set up that way, and we chose not to go through it because
we believed to do so would ultimately not be in Australia's interests."
An official from the French Embassy in Canberra said an
intergovernmental agreement should have allowed for confidential
discussions between ministers about changes to political or strategic
circumstances.
"No warning, no proposals for discussion were offered," the official
said, speaking on condition of anonymity because of the sensitivity of
the matter.
OFF-RAMPS AND GATES
The deal was first announced in 2016. A pre-design review was delayed in
2018 because the "work provided to Defence by Naval Group did not meet
Defence's requirements", the audit said, citing lack of design detail,
operational requirements and 63 studies not completed.
The contract between Australia and Naval Group, majority owned by the
French government, was signed 16 months late in February 2019.
It included contractual off-ramps in which Australia could pay to exit
the project, and established "control gates" whereby Naval Group must
meet criteria before progressing to the next phase. The defence
department considered these "hold points" for assessing the project's
risk, the auditor-general said.
In September 2019, with A$446 million ($325 million) already spent in
France, the defence department told the auditor it had examined
extending the life of Australia's Collins-class submarine fleet "and the
time this would allow to develop a new acquisition strategy".
[to top of second column]
|
A Rivercat ferry passes by the Royal Australian Navy's Collins-class
submarine HMAS Waller as it leaves Sydney Harbour on May 4, 2020.
The Australian government has considered extending the life of the
Collins class as it examines the fate of its next-generation sub
program./File Photo
The 2020 Auditor-General's report examining the
submarine deal - the Department of Defence's biggest ever - found
the department had been "frank and timely" in communicating concerns
with Naval Group.
Naval Group said in a statement to Reuters that it was aware of
public discussion, but that official declarations were supportive of
the submarine programme. It said Morrison was "very clear that the
decision was not a result of difficulties with the Future Submarine
Program or Naval Group".
"Naval Group delivered on its commitments to the Commonwealth of
Australia as acknowledged by the letter for termination 'for
convenience' we received," the statement said.
In August, the Australian and French defence ministers, and French
foreign minister, "underlined the importance" of the submarine
programme, according to a joint statement from both countries.
REVIEW PANEL
According to the Auditor-General's report, the most recent major
milestone in the French contract - a preliminary design review - was
in January 2021.
An industry source with direct knowledge of the matter told Reuters
that Naval Group Australia provided material to Defence in "late
January or February", but that Australia did not consider it to meet
requirements.
Morrison's office created a panel in January to advise an inner
circle of his Cabinet on how to proceed with the programme, contract
notices and parliament records show.
In June, senators, including Patrick, asked panel chairman William
Hilarides, a former vice admiral in the U.S. Navy, if it had advised
the government to cancel the French contract.
Hilarides, who had overseen ship and submarine construction for the
U.S. Navy, said the panel's advice was confidential.
The former head of BAE Systems Submarines, Murray Easton, who had
turned around a delayed British nuclear submarine programme, joined
the panel in February, contract notices show.
It met by videoconference 10 times by June, including confidential
briefings for its U.S. members at the Australian embassy in
Washington, the parliament was told.
Easton and Hilarides did not respond to requests for comment.
($1 = 1.3755 Australian dollars)
(Reporting by Kirsty Needham. Editing by Gerry Doyle)
[© 2021 Thomson Reuters. All rights
reserved.] Copyright 2021 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content. |