Logan County Courthouse
contractors prepare departments for fall and winter moves to install
Geothermal, HVAC and lighting
Send a link to a friend
[August 15, 2022]
At a special Logan County Board meeting on August 8,
board members and several county employees heard an update on the
impending schedule for the next phase of the courthouse restoration.
Project Manager Bill Walter of MRTS said the next phase will be the
performance contract portion of the restoration. This portion deals
primarily with outside well fields being drilled, the interior HVAC
system being installed and associated electrical and plumbing that
goes along with it.
With the construction management portion, they were about a week
away from putting out advertising for bids. When bids come back,
Walter and others involved will look and see whether the prices are
favorable.
For the performance contract, Walter said they went round and round
with several options to keep the price reasonable. They also spoke
with many contractors.
Representatives from the companies CTS and Veregy detailed how the
project would be laid out and how it would affect everyone’s office
when they need to free up space to work.
Material availability has caused delays, so Walter said making a
schedule has been a challenge. He said questions during the
presentation would be acceptable.
Next, Walter introduced John Mihulka, the project manager for the
performance contract. He gave a general presentation of how Veregy
would be proceeding with their work beginning around September 12 to
December 5.
The well fields that will be drilled will be in the main grass area
on the south part of the courthouse and around the corner to make an
“L” shape. Veregy will put fencing around the are where the well
fields will be drilled. With the exterior work, machines will be
drilling large holes. Mihulka said this area will be clearly marked.
The fencing will act as a barricade against any construction
activity that will be happening.
People will continue to have access to the south entrance and
outside elevator but will need to enter from the Pulaski Street or
Broadway Street sidewalks.
Drilling the well fields should take about two months from
mid-September to mid-November with lines going to the basement. A
couple times when piping is being put into the building, Mihulka
said the east side to get to the Mclean entrance of the courthouse
will not be accessible.
Electricity from the new transformer will also go in from the Mclean
side.
Out of the two to two-and-a-half months, Mihulka said there should
just be two to four days the courthouse cannot be accessed from the
south entrance.
Based on anticipated availability of parts, Walter asked the Veregy
representative to share when the third floor needs to be evacuated.
Around Mid-December, Mihulka said geothermal pumps may arrive. Heat
pumps are likely to be in then too. Prior to that, they will be
running piping and electric into the building. He anticipates
employees on the third floor may possibly need to be moved sometime
in November.
What Mihulka does not want to do is over schedule and then have a
delay due to parts not arriving when anticipated. By the next
meeting, he hopes to have a much more concrete schedule for the
interior work.
Up until this past week, Walter said October 1 was a day they were
shooting for as far as needing to start moving people. He said there
is no sense moving people when it is not necessary. Waiting to move
people will give them more time to plan what and who needs to be
brought over to the Orr Building.
As contractors get further into work, Walter said things will be
firming up. By September 20, Walter will give another update with
firmer information on material availability.
Even then, Walter said if there are any surprises in delivery in
October, adjustments could be made before moving offices. He would
be positive things are happening when people are asked to move.
With one primary component, Walter said it has been promised in
February. However, he said they plan to do some creative engineering
to circumvent the need for that part and substitute it with
something equal or better. That way, they will not have to wait so
long for the part.
By then, Walter said everything else should be completed
substantially. All that will be necessary is to put in electrical
plumbing.
From a practical standpoint, Logan County State’s Attorney Brad
Hauge then had a few questions. Hauge asked about hours of
operation, how the work would impact parking and what noise level to
expect.
Mihulka said most work would be done between 7 a.m. and 3:30 p.m.
There would be some noise, but he said they would not be pounding or
breaking concrete. They will be using a drill that goes down into
the ground.
Occasionally, there may be some specialty work done at night.
For asbestos abatement, Walter said they have talked about utilizing
the opportunity to work on the weekends.
In specific localized areas of the first and second floors, Walter
said some work may be done during evenings or weekends.
Parking will not be affected any more than it is now. Since the work
being done outside will be in the grassy areas, it will not affect
equipment in parking areas. Mihulka said they would park where the
county asked them to park. Pedestrian access will only change due to
rerouting.
A large television monitor will be put up in the courthouse showing
all photographs being taken. Walter said there will also be
information about the restoration going across the screen. He will
be sending out emails to update employees on what is happening and
what access may be affected.
In upcoming weeks, Logan County Treasurer Penny Thomas said there
will be many people coming in and out of the courthouse because of
property tax due dates. She wanted to know if that would be affected
by work going on outside.
Even with the work going on, Michelle James of CTS said people would
still have access to the entrance.
To direct people, Thomas asked about them putting up signs. When the
scaffolding was first put up over the main entrance, Thomas said
some were confused and thought the courthouse was closed.
Walter said they could make sure there are signs out saying “enter
here” and follow red or green arrows.
[to top of second column] |
Election equipment will be delivered and there were concerns
about how the work would affect that.
Logan County Sheriff Mark Landers said they would need to coordinate that.
The Veregy representative said there will still be accessible
areas.
If fencing goes up September 12, Mihulka said drilling of the 40 well fields
will take approximately eight weeks. The well fields will then be tied into the
building. Access will be coordinated then.
Some days, the accessible elevator may need to be accessed by coming in from the
Pulaski Street side. When the electrical tie in is done, Mihulka said entrance
will need to be from Broadway Street.
During the construction management phase, Walter said he does not see a need to
block the ramp. There will be special lay down areas and they will make sure the
ramp is partitioned.
At the October board meeting, Walter said they may tell employees [on the third
floor] they need to start moving by November 1. There will be additional updates
in November and December. He said they keep getting more information every day.
Board Vice Chairman Scott Schaffenacker next asked how work on the dome is
going.
With the dome work, Walter said things are going well if not better than what
had been anticipated with the schedule. Their goal is to have the dome work
substantially complete sometime in October.
Walter said they will coordinate and hope to have the copper and cupola
installed before the end of October.
In late October or early November, Walter said they will start dismantling the
steel scaffolding. His intention is to have everything off the roof, scaffolding
and steel wise, in the month of December, though the date is not yet certain.
For clarification, Hauge asked if after moving people out of the third floor in
November, people from the second and first floors would be moved later. He
wanted to know how long the moves would last.
Logistics and certain processes are what Walter said they will have to rely on.
They could be out between two and four weeks. He said they understand there is a
lot of movement that has to happen and it could be December or January when
others are moved.
The act of moving employees from the third floor is something Walter said will
act as a training ground. That move will show how smoothly everything went, what
was involved and how many people are required to move.
Hauge asked if everyone on the third floor would be moved at once or if it would
be just one half and then the other half.
Ideally, Mihulka said everyone on the entire floor would be moved.
The second phase interior work with geothermal will be done in a loop. Mihulka
said it will go up to the third floor then down to other floors.
The first interior phase will be longer. Mihulka said they will not only be
doing work on the third floor and basement but will also bring risers up.
Once the loop is created and they get it commissioned, Mihulka said when they
move people from the third floor back, the loop will already be engaged. When
that part is done, he said they will have a better idea of how the rest will go.
Since new lighting and a ceiling grid will be added, Walter said workers will
need access to the entire floor.
There will be meetings with department heads once work is being done inside.
Walter and the contractors will tell the department heads what needs to be moved
and how it can be moved. He does not think it will be necessary to move
everything out of offices.
If people need to get access to their offices to get files still in there,
Walter said there will be protocols.
Some files are stored in the basement and Gil Bucio of CTS asked if departments
anticipate needing access to them. Bucio was asking because some basement files
will need to be moved to create space for contractors to install piping.
In the Circuit Clerk’s office, Logan County Circuit Clerk Kelly Elias said they
access files in the basement daily.
To ensure employees know where the files are put, Bucio said moving the files
will have to be carefully coordinated.
Because there are quite a few files, Elias feels like maybe they should be moved
now. Her department is in the middle of a major scanning project, so Elias would
have liked to know months ago before she moved files. She asked for better
communication.
Walter would like to meet with departments individually so they can take
contractors to these areas. The performance contractors can help determine how
much needs to be moved.
The IT department is housed in the basement. Therefore, Landers asked if IT
would need to be moved out of there.
IT is in the center of the basement, so Walter said their movement would be
minimal if needed at all.
When Walter and contractors meet with department heads individually, he said
they could show drawings. They will be very detailed about what will need to be
moved.
In the event workers are in the courthouse at night, Facilities Manager
Christopher Wilson asked about security.
All contractors are vetted, so Landers said security is not a big problem.
If work needs to be done at night, Walter said they would let people know way
ahead of time.
County Employee Lisa Bobb asked how they could be assured the building is safe
when scaffolding has been up for nearly two years.
The scaffolding is inspected quarterly. Walter said there have been a few
adjustments due to wind. Employees are still safe.
If anything, Walter said they have overcompensated and overbuilt. They went
above and beyond to ensure safety.
Everything that was compromised is now gone including the plaster above the drop
ceilings. Walter suggested, to emphasize his point, that he would feel safe
inside the courthouse in a tornado.
[Angela Reiners] |