Aerospace manufacturers placing orders earlier to beat parts shortages
Send a link to a friend
[October 21, 2022] By
Allison Lampert
ORLANDO, Fla. (Reuters) - The shortage of
parts from chips to windshields that has held back plane production will
run into at least 2023 - and manufacturers are spending more to tackle
the problem, aerospace executives said.
Manufacturers are ordering material as far as two years in advance – a
break with just-in-time models used previously to restrain costs – and
dispatching specialized staff to keep production lines running,
executives said at the world's largest business jet show in Orlando,
which ended on Thursday.
However, parts shortages are expected to continue dogging U.S.
planemakers and large aerospace suppliers, which report quarterly
earnings next week.
Supply-chain disruptions cost aerospace and defense companies an average
of $160 million in lost revenue for the prior year, according to a
first-quarter survey of aerospace companies, said Jennifer Bisceglie,
chief executive of supply- chain risk management company Interos.
Executives from Honeywell International Inc, Textron Aviation and
General Dynamics Corp's Gulfstream Aerospace told Reuters at the
National Business Aviation Association show they are taking greater
steps to back suppliers.
Vipul Gupta, vice president and general manager of Honeywell Aerospace
Avionics, said his division is ordering parts two years out, compared
with previous lead times of roughly 60 days to 10 months, depending on
the component.
For simple avionics components, lead times have increased to roughly one
year, compared with 90 days in the past. Honeywell makes products like
avionics and engines for business jets and flight management systems for
commercial jets.
"The story is very simple: getting our forecast right and putting the
demand in front of our suppliers a lot earlier," Gupta said. "It
provides a very clear picture for our suppliers on what they need to
deliver."
Gupta said his division would support European planemaker Airbus SE's
longer-term production goal of 75 A320 family jets a month in 2025, up
from around 50 in 2022. Some manufacturers have questioned whether a
battered supply chain could keep up with the target.
"If they want to execute 75, we will execute 75," he said.
Smaller suppliers, struggling with higher costs and labor shortages, are
pushing manufacturers to order many months in advance to assuage
concerns over a possible economic slowdown.
[to top of second column] |
Gulfstream Aerospace pilots stand amid
their aircraft, including their newest jet, the G700 at the National
Business Aviation Association (NBAA) convention and exhibition in
Orlando, Florida, U.S. October 17, 2022. REUTERS/Gregg Newton
But ordering earlier also means making payments sooner, raising
working capital, and delaying when manufacturers can recoup expenses
on the plane or part's delivery.
ROBUST ORDER BOOK
To mitigate additional costs, some private planemakers are asking
customers for larger deposits on jets before delivery, said one
corporate planemaker executive who asked not to be identified.
Business aviation rebounded faster than commercial traffic in the
United States last year as wealthy travelers opted to fly on private
jets and avoid crowded airports during the height of the COVID-19
pandemic.
Gulfstream Aerospace orders roughly six months to a year out,
compared with a previous "just in time" strategy, President Mark
Burns said.
Burns said the company's robust order book has more than offset any
possible impact on working capital.
Longer lead times also add an additional risk of unwanted inventory
in the event of a downturn, analysts say.
"The longer lead times stay high, the more of a risk to earnings in
our view," Bank of America Global Research analyst Andrew Obin said.
That has companies supporting constrained suppliers with advice and
staffing like machinists and engineers, often at the same time.
"The only caveat is if we send you help, you have to work on our
stuff first," said Ron Draper, president of Cessna business jet
maker Textron Aviation in an interview.
"We’ve been at some of these suppliers and we see a lot of other
OEMs in the visitor logs."
Still, Gulfstream Aerospace's Burns and others are more optimistic
about supplier performance with deliveries getting closer to the
desired dates.
"We've kind of plateaued and will see improvements into 2023."
(Reporting by Allison Lampert in Orlando, Fla.; Additional reporting
by Rajesh Kumar Singh in Chicago and Abhijith Ganapavaram in
Bengaluru; Editing by Kevin Krolicki and Matthew Lewis)