Location, location, location: U.S. manufacturing boom has a real estate
problem
Send a link to a friend
[April 13, 2023] By
Timothy Aeppel, Ben Klayman and Nichola Groom
(Reuters) - Volkswagen's off-road brand Scout Motors studied 74
different parcels of land across the U.S. last summer as it hunted for a
place to build a $2 billion assembly plant.
It quickly eliminated almost all of them. In one case, they learned it
would take six years to build a needed rail link. Others lacked access
to clean power - crucial for a project for "green" electric vehicles.
Some did not offer enough nearby skilled labor.
"We were hitting a deadline," said Scott Keogh, Scout's CEO, so they
settled for a parcel in South Carolina that has all their desired
features but is a bit smaller than they initially wanted - 1,600 instead
of 2,000 acres.
Scout's scramble highlights a challenge facing dozens of global
manufacturers. Fueled by a combination of hefty government incentives, a
transition to new transportation and energy technologies, and national
security concerns about relying on distant suppliers, especially in
China, there's a factory-building boom taking place across the U.S.
But all that new construction has a real estate problem. More
specifically, a "megasite" problem. While the U.S. has plentiful land,
there are not that many places to quickly plunk a billion-dollar-plus
factory.
The factory renaissance could soon hit a barrier because of the scarcity
of ready-to-go megasites, according to 25 economic development groups,
state and local officials, utilities, and companies interviewed by
Reuters.
That would be a problem for the Biden administration, which has pushed
through legislation to fuel the developments. Corporations have
announced dozens of projects since the passage of the Inflation
Reduction Act and the CHIPS Act last year.
A White House official said it was a "high-class problem" to have,
adding: "Folks are finding places to build. I don't think I've heard of
one company abandoning plans to go forward because they're not able to
find a site."
AGGRESSIVE TIMELINES
There’s no single definition for a megasite, but it generally refers to
a very large plot — one common threshold is 1,000 acres — tied to
transport, low-cost and preferably renewable energy, and a nearby supply
of skilled labor.
Local economic development agencies and states have long cultivated big
industrial developments by assembling land and installing utilities in
the hope of luring the next big auto assembly or steel plant with the
promise of fast-track building.
Speed is often key. When electric vehicle maker Rivian Automotive Inc.
was hunting for a place to build a $5 billion plant, it considered a
spot just outside Fort Worth, Texas.
But the EV-maker "had some pretty aggressive timelines as far as when
they needed certain elements of the transportation infrastructure in
place," said Robert Sturns, director of the Fort Worth Economic
Development Department. Fort Worth could not meet those, and the project
jumped to Georgia in late 2021.
The requirements on megasites can be very specific. Intel Corp's $20
billion semiconductor plant going up in Ohio could not be situated too
close to a rail line, since passing trains can create unacceptable
vibrations, according to the company.
Even smaller factories can find it difficult to build quickly in this
environment.
CubicPV, which makes silicon wafers used in solar panels, launched a
nationwide search for a 100-to-130-acre site immediately after the IRA
passed last August. They have a tight time frame, said Todd Templeton,
the company's chief commercial officer, since IRA tax incentives start
to phase out at the end of this decade.
They studied hundreds of sites but constantly hit roadblocks. Some
locations said it would take two or three years just to get utilities
installed, said Templeton. They are choosing from two good possibilities
and are aiming to have the plant open by 2025.
[to top of second column] |
U.S. President Joe Biden attends the
groundbreaking of the new Intel semiconductor manufacturing facility
in New Albany, Ohio, U.S., September 9, 2022. REUTERS/Joshua Roberts
One site selection executive, Gregg Wassmansdorf, a senior managing
director of global strategy consulting with Newmark Group Inc.,
estimates fewer than two dozen true megasites are still available
across the country at widely varying stages of development.
"Every company, of course, wants shovel-ready megasites," said
Christopher Chung, chief executive of the Economic Development
Partnership of North Carolina. "But those are more or less pretty
picked over with a couple of exceptions here or there."
A POWER PROBLEM
Didi Caldwell, president of consultancy firm Global Location
Strategies in Greenville, South Carolina, uses a database from fDi
Markets, a London-based firm that tracks major cross-border
investments worldwide, to gauge how fast demand for megasites has
grown in the U.S.
According to that source, she said, there were 20 industrial
projects with investments over $1 billion and a promise of creating
at least 1,000 jobs announced last year in the U.S. - up from 15 the
year before, and only eight the year before that.
In the decade and a half before the recent spike, the annual average
was just over five and many years saw just three or four large
projects announced.
One major constraint, particularly for energy-hungry factories such
as battery plants, is the need for large amounts of electrical
power.
"Some of these projects require hundreds of megawatts," said
Caldwell. "At the same time, we're shutting a lot of coal plants."
While the U.S. is investing heavily in building green power sources,
those projects also face delays. A report by Lawrence Berkeley
National Laboratory found that a typical project built in 2022 took
five years from the initial request to interconnect it with the
electrical grid to commercial operations, up from three years in
2015.
The cost and difficulty of building new long-distance transmission
lines has also soared in recent years, said Rob Gramlich, president
of Grid Strategies LLC, an engineering and economic analysis firm
focused on the power industry.
There's a rush to prepare more megasites. Michigan just created
four. The governors of South Carolina, Virginia and North Carolina
have each proposed to spend hundreds of millions of dollars on
readying industrial sites in the coming years. Illinois this year
will allocate $40 million in grants to prepare existing sites for
companies seeking to move quickly.
But creating new megasites is inherently difficult. Environmental
regulations often limit developments, local communities sometimes
oppose them, and the sheer scale of the projects often require just
the right mix of conditions to make it feasible.
To be sure, companies want more megasites for pocketbook reasons.
"The reason they would like more megasites, of course, is that then
they could compete for better pricing" when they have more options
to choose from, said Mike Tracy, principal of the Agile Group, which
advises companies like automakers.
There are also the intangibles.
The VW Scout plant, for instance, is situated in clear view of a
major interstate highway connecting South Carolina's coastal regions
to the upper Midwest. That means putting the Scout name, being
revived by VW after four decades of dormancy, in sight of tens of
thousands of passing motorists a day.
"We have a lot of people who are coming from the north or from the
Midwest down that highway that would drive right by that facility as
they go to the beaches of South Carolina and Georgia and Florida,"
said Harry Lightsey III, South Carolina’s secretary of commerce.
"That was all important."
(Reporting by Timothy Aeppel in New York, Ben Klayman in Detroit and
Nichola Groom in Los Angeles; Editing by Dan Burns and Claudia
Parsons)