Amtrak, which contracted with Alstom to develop and manufacture
28 new high‐speed trainsets, initially was scheduled to begin
customer service in May 2021 and has spent $1.6 billion on the
program.
The Amtrak inspector general in a report on Tuesday said the
program faces further delays because the new Amtrak trains have
not met Federal Railroad Administration (FRA) requirements and
all of the trainsets produced so far have defects. The Acela,
which operates on the Boston to Washington Northeast Corridor,
is Amtrak's most profitable business line.
The report added the likeliest cause of more delays would be a
lack of a validated trainset model, followed by certain trainset
defects. The report said the current estimate is for service to
begin after June 2024. Amtrak said it was working closely with
Alstom as they complete testing and modeling, adding the 2024
start date is based data received from Alstom.
The report said Alstom must still produce a validated computer
model of the trainset "that proves the new designs are safe to
proceed with required testing" in order to proceed with
operational testing and to be able to run new trains at planned
faster speeds of 160 miles per hour (257.5 km per hour).
Alstom said it is working with the FRA to meet requirements
"through their first-ever safety certification for high-speed
trains." FRA did not immediately comment.
Alstom said it has successfully run these trains on a test track
at high-speed and on the Northeast Corridor for nearly 70,000
miles. It said planned modifications "along with additional
changes that Amtrak requested are in no way in the critical path
of completion of this project."
Amtrak wants to double ridership nationwide by 2040 after its
ridership grew 45% from 2003 to 2019 to 32.3 million riders.
Congress approved $66 billion for rail as part of the 2021
infrastructure bill, with Amtrak receiving $22 billion. The bill
also sets aside $36 billion for competitive grants.
(Reporting by David Shepardson; Editing by Mark Porter and Josie
Kao)
[© 2023 Thomson Reuters. All rights
reserved.] Copyright 2022 Reuters. All rights reserved. This material may not be published,
broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content.
|
|