Lincoln Aldermen approve mill and
overlay projects for 2024 pending availability of funds in the
2024-25 budget
Tremont Street not on the list as
presented
Send a link to a friend
[February 21, 2024]
The
second voting session of the month for the Lincoln City Council was
held on Tuesday, February 20, 2024, due to the Presidents Day
holiday on Monday the 19th.
Among the topics voted upon was a motion to approve, pending budget
approval, the 2024 Mill and Overlay Projects, coupled with the 2023
projects not yet completed.
This is a push to get an earlier start on city street projects, with
the goal of continuing to work for target identification and
approval earlier each year, until the projects are well in line to
be started and completed in the earlier parts of the summer instead
of in the late summer to mid-fall.
The council approved mill and overlay targets from 2023 that
included the following:
Third Street from Decatur to Maple - $129,200
Chicago Street from Clinton to Wyatt - $191,000
Wyatt Street from Chicago to Kickapoo - $84,700
McLean Street from Decatur to Wyatt - $158,500
The mill and overlay projects for 2024 include the following:
Union Street from the bridge to Lincoln Parkway - $266,200
Eighth Street from Pine to Union - $284,000
Kankakee from Broadway to Peoria - $271,700
An additional target in the 2024 plan is Union Street from Woodlawn
to the Brainard’s Branch Bridge ($274,100.). This project is part of
the Union Street Lift Station Project and would be covered by Sewer
Enterprise funds.
Funding for the other projects would come from two
sources. The city has $529,000 in Rebuild Illinois Grant Funds. This
funding would be applied to qualifying streets in Lincoln, then the
city general fund will be responsible for the remainder. The total
dollar amount for the carried over 2023 projects plus the new 2024
projects comes to $1,699,400. Rebuild Illinois would pay $529,000.
The Sewer Enterprise Fund would pay $274,100 leaving the city to
come up with $866,300 in the 2024-25 budget for the remaining
projects.
The budget committee for the city is working on the draft documents,
which will be reviewed by the full council sometime within the next
month. The budget for the new fiscal year takes effect on May 1, and
must be approved before that date.
The one much needed and desired project that is not
on the list for this coming season is the mill and overlay for
Tremont Street from North Logan to Union, though at one time it was
a primary target.
There has been a complication in doing that street project.
The original plan included using the $529,000 from the Rebuild
Illinois Grant to cover right at 50 percent of the total cost of the
project. The city would then need to pay the remainder from the
general fund.
However, as it was explained to the council at the February 13th
workshop meeting, there is an issue with one section of the street
because the property at the corner of Tremont and Ottawa Streets is
on the National Historic Registry.
At the workshop meeting, Street Superintendent Walt Landers
explained that the street could have been eligible for Rebuild
Illinois Funds, but before the city could use those funds, it would
require that there be a confirmation as to where the line stops on
the historic site documents.
Landers said that if the property is designated as an
historic site all the way to the curb of the junction streets, then
the city would not be able to re-design the sidewalk and steps at
that corner. If the historic designation ends at the retaining wall
then the city could alter the corner. In order to know this, a
request has to be made to the state Historic Preservation Office. It
could take 15 to 18 months for that organization to return an
answer. Landers said that the Rebuild Illinois Fund has to be
expended by 2025, so there is not enough time to get through all the
processes and still do the project before the time runs out to
expend the grant.
[to top of second column]
|
A second option for Tremont would be to do the entire
project using city general funds. Then there would be no call for a
response from historic preservation. However, the total project is
going to cost right at $1,000,000 which is more than the city
budgets annually for all mill and overlay projects.
If the city wants to do Tremont, then it would be the only project
that could be done in a season.
Shane Remmert with Crawford Murphy and Tilly was on
hand for the workshop meeting and corroborated Landers explanation.
For the record, he submitted a letter to Landers from himself and
fellow engineer Kristin Timmons.
The letter said:
“The City had previously targeted using
Rebuild IL funds for the reconstruction of Tremont Street. IDOT will
allow the use of these funds for this project; however, after
further investigation, CMT would advise against it due to the home
on the southwest corner of Tremont & Ottawa being on the National
Historic Registry. Since this is listed as a historic property,
during the Environmental Survey Request (ESR) phase of the approval
process, IDOT will forward the project on to the State Historic
Preservation Office (SHPO). SHPO will then review the potential
impacts to the historic property. If they determine that any
"contributing elements'' to the actual dwelling are adversely
affected, this will trigger a Section 106 review that must be
approved by both the IDOT and the Federal Highway Administration (FHWA).
Depending on their determinations, these potential review hurdles by
additional state and federal agencies could take up to 15 to 21
months to complete. As such, we believe that Tremont Street is not a
good candidate for using Rebuild IL funds which need to be
authorized prior to July 1, 2025.
“We have discussed several potential project options with you and
completed a cursory review of each. At our last discussion
concerning the Rebuild IL funds, it was decided to target using the
funds to supplement the City's 2024 Resurfacing Program to try to
stretch the City's dollars even farther. If acceptable to the
Council, we would recommend using a mix of Rebuild IL funds, MFT
funds, and City funds for the 2024 Resurfacing Program. As far as
Tremont Street is concerned, CMT can begin preliminary engineering
design and Agency coordination in 2024 once an engineering agreement
is approved by the Council. CMT can develop a phasing plan to
complete the project over multiple construction seasons to limit the
impact of construction costs to the City's budget if that is
desired.”
At the workshop meeting, Alderman Steve Parrott said that he was
very disappointed by the news. He said that the street is in bad
repair and has been in need of work for quite some time.
Alderwoman Wanda Lee Rohlfs said that since the closure of Pekin
Street at the railroad crossing, Tremont had become much more
traveled as a route from the heart of the city to Union Street and
on west. She said that the increased traffic is further damaging the
road, and drawing even more attention to the need for repair.
Aldermen discussed alternatives and it was suggested
by Alderman Kevin Bateman that the only real answer considering the
price tag of the project was to for one year, make a repair to only
that one street.
While that was not a popular suggestion, alderman also recognized
that it could be the only answer.
Parrott asked if the city could do a part of the project one year
and another section another year. Landers said the nature of the
work that needs to be done to make the street good did not lend
itself to being done in segments. The preferrable answer would be to
have funding for the entire project to be done at one time.
There was discussion of at least getting started with the
engineering and design work, and that may be a feasible move,
pending budget constraints.
Because of all this, the aldermen agreed to remove Tremont Street
from the upcoming year projects for the vote on this past Tuesday
night.
It was mentioned prior to the vote that the approval of the projects
now is still pending and could be subject to change during the
budgeting process over the next few weeks.
The vote was taken to approve the project list as presented and
passed unanimously with seven aldermen present. On Tuesday evening,
those present included Bateman serving as Mayor Pro Tem, David
Sanders, Robin McClallen, Parrot, Sam Downs, Rohlfs and Rhonda
O’Donoghue.
[Nila Smith] |