Boeing finalizes 737 MAX guilty plea deal, US outlines reasons
Send a link to a friend
[July 25, 2024]
By David Shepardson, Allison Lampert and Chris Prentice
(Reuters) -Boeing finalized a guilty plea to a criminal fraud conspiracy
charge and agreed to pay at least $243.6 million after breaching a 2021
agreement with the U.S. Justice Department, according to a court filing
on Wednesday.
The planemaker allowed potentially risky work at its factories and did
not ensure key airplane record keeping was accurate or complete, the
Justice Department said as it outlined why it believed the planemaker
had violated the 2021 deferred prosecution agreement.
Boeing on July 7 agreed in principle to plead guilty to conspiring to
defraud the Federal Aviation Administration after the government said
the planemaker knowingly made false representations about key software
for the 737 MAX.
Boeing confirmed on Wednesday that it had filed a detailed plea
agreement with the Justice Department. "We will continue to work
transparently with our regulators as we take significant actions across
Boeing to further strengthen our safety, quality and compliance
programs," the company said.
The Justice Department said in May that Boeing had breached its
obligations in the agreement that shielded the planemaker from criminal
prosecution stemming from misrepresentations about a key software
feature tied to fatal 737 MAX crashes in 2018 and 2019 that killed 346
people.

The finding was made in the wake of a January in-flight panel blowout on
an Alaska Airlines 737 MAX that exposed continuing safety and quality
issues at Boeing, just two days before the 2021 agreement shielding it
from prosecution over the previous fatal crashes expired.
DOCUMENTATION NOT COMPLETED
The Justice Department said in its court filing that Boeing failed to
ensure employees documented removal of parts during manufacturing of an
airplane and it did not ensure mechanics and inspectors who stamped they
completed work had actually done so.
The Justice Department said Boeing in April disclosed false stamping at
its 787 plant in South Carolina by some employees. The FAA said in May
it was investigating after Boeing said some employees at the plant had
committed "misconduct" by claiming some tests had been completed.
Boeing also did not ensure work on airplanes was conducted in the proper
sequence, the Justice Department said.
[to top of second column]
|

A Boeing 737 Max aircraft during a display at the Farnborough
International Airshow, in Farnborough, Britain, July 20, 2022.
REUTERS/Peter Cziborra/File Photo

"Boeing senior executives prioritized the movement of aircraft
through Boeing’s factories over reducing out-of-sequence work to
ensure production quality," the filing said. "Out-of-sequence work
is more difficult to perform (and) increases the risk that defects
in manufacturing will occur."
The Justice Department has a separate criminal probe ongoing into
the Alaska Airlines jet that was missing four key bolts. Boeing has
said no paperwork detailing the removal of the bolts was completed.
As part of the guilty plea deal, Boeing agreed to pay the maximum
fine of $487.2 million and the DOJ recommended the court credit its
previous 2021 payment of $243.6 million against that.
The planemaker also agreed to spend at least $455 million over the
next three years to boost safety and compliance programs, said the
filing, adding that was 75% higher than Boeing's previously planned
expenditures on its corporate compliance program.
Families of those killed in the MAX crashes will be able to file
objections within a week before Judge Reed O'Connor, who will decide
whether to accept the deal and determine if Boeing owes restitution
to the victims' relatives.
Boeing's board will have to meet with the relatives within four
months of sentencing, the filing added.
The deal also imposes an independent monitor, who will have to
publicly file annual progress reports, to oversee the firm's
compliance. Boeing will be on probation during the monitor's
three-year term and it can be extended by a year if Boeing does not
comply with the terms.
(Reporting by David Shepardson, Allison Lampert and Chris Prentice;
Editing by Chris Reese and Jamie Freed)
[© 2024 Thomson Reuters. All rights
reserved.]This material
may not be published, broadcast, rewritten or redistributed.
Thompson Reuters is solely responsible for this content.
 |