Logan County Board
Building and Grounds committee hears restoration updates from Bill
Walter
Send a link to a friend
[June 06, 2024]
The
Logan County Board Building and Grounds Committee met for its
monthly session at 5:30 p.m. on Tuesday, June 4th, 2024. Five of the
six board members for this meeting were present. Those present
included Jim Wessbecher (Chairman), Hannah Fitzpatrick (Vice
Chairman), Michael DeRoss, Robert Sanders, and Kathy Schmidt. Not
present was Emily Davenport.
During the meeting, board members heard from Bill Walter, Masonry
Restoration Technologies & Services, LLC. As the project manager for
the Logan County Courthouse restoration project, Walter discussed
many aspirations for making improvements to the courthouse. These
include new carpet, doors, door frames, windows, concrete
replacement at the courthouse, and roofing for the bandstand in
Latham Park.
Currently, the courthouse is undergoing third floor renovations.
Judge Jonathan Wright has selected a dark blue carpet for the
courtroom as well as the adjoining walkway to the deliberation room.
This carpet color was picked out to match the woodwork, paint, and
seats in the courtroom. The builders and Walter are debating if that
same carpet should also be used in the first and second floor
courtrooms to maintain continuity.
The committee agreed that it was a good idea to maintain continuity,
so everything matches together well. They approved this project with
everyone in favor.
Walter expressed a recommendation for a particular wood door and
frame that would match all the other doors in the courthouse. There
was a door that was already an existing door in the courthouse
selected for this particular project, but it didn’t fit. There is
another door in the courthouse that is the right size that’s coming
from a location that’s not used frequently. The plan is to move that
door to the more frequently used area and put a new door at the top
of the wheelchair lift that goes into the courtroom. This project
would cost $1,845 to be able to make the swap work, which Walter
thinks is a good price. He has already cleared this project to be
based on the ADA standpoint.
The committee approved this project with everyone in favor.

Walter and his team are replacing all the windows in
the courthouse. During their time exploring options, they found that
there is an existing wood frame that is in great condition that was
hidden by the metal frame in the 90s. When they removed the metal
frame, they found the historic frame and would like to preserve it
if possible. However, they have discovered that the sealant used for
the wood frame contains asbestos. The cost of removing the asbestos
would be great. Therefore, Walters is not recommending that the
original wood frame be exposed. Walter is requesting a change order
that will include a metal frame complimentary to the window that
would cover the historical wood and provide the right dimensions for
the new window sash to operate as it is supposed to. He specified
that this would be a smart plan just in case someone wanted to go
back to the historical wood frame years from now. The original quote
for the project came in high in Walters opinion, Walter expressed
his concern with the contractor and was able to get it a $4,500
reduction from the original bid of $41,225 for all the windows to be
replaced.
[to top of second column] |

The committee approved this
project with everyone in favor.
The next matter was about the concrete replacement, but Walter
did not come with a plan drawing that indicated what each price
reflected. He asked for this portion of the plan to be tabled
until he can create a proper blueprint of each price and item
that it would belong to. He did mention that a portion of the
concrete replacement will be at the expense of the scaffolding
company because it is damage incurred by the scaffolding.
Wessenbecher requested that when Walter came back with a
blueprint that he also outline what the board would and wouldn’t
be paying for, and Walter agreed.
The committee agreed to table this.

Walters finished with some updates on the restoration
of the Latham Park Bandstand Pavilion. He said that the new roof on
the bandstand will be started soon. There is a steel entry door that
goes into the underneath portion of the pavilion that’s not in great
condition and requires a lot of effort to get open. The price to
replace would be $1,965. Walter stated that for what they are
providing, this is a good price. A new door would provide a proper
latch and lock and wouldn’t require a crowbar to enter anymore. The
current door requires a ton of effort to get into and also poses the
risk of injury.
The committee approved this project with everyone in favor.
Walter also mentioned concerns that don’t need to be taken care of
at this present time. One of those concerns was about the
lantern-like lighting in the pavilion, and a submission of a crack
in the tile floor in the courthouse that caused great concern for
the uprightness of the building. The architects contacted a
consulting engineer that happened to be in the general area and
could make an appearance to take a look at the tile floor. He
reassured everyone that there was no current impending danger and
wasn’t a concern at that time. However, in the last couple of weeks,
the same engineering company ended up emailing an invoice to Walter
specifying that $5,000 was the price for the checkup service. Walter
specified that he wants to express his disappointment to the
engineer and that he does not plan on paying that invoice.
The board also approved the Verderber family Scully Park bench
donation The new bench will match the one that was previously
donated by the Lincoln Woman’ Club.
All the items brought before and approved by the Building and
Grounds committee will go before the full board at the monthly
workshop and voting meetings for final approval.
The county board has issued a change of date for the workshop
meeting, which was originally scheduled for Thursday, June 13th. Due
to the CoGFA public hearing that same night, that committee of the
whole will meet on Wednesday, June 12th at 6 p.m. in the first floor
courtroom of the Logan County Courthouse.
[Shelbi Fisher]

|