Lincoln aldermen hear two plans
for Tremont Street
Send a link to a friend
[February 29, 2024]
Tuesday
evening, February 27, 2024 the Lincoln City council met for the
second Committee of the Whole meeting for February. The agenda was
light with one priority topic regarding Tremont Street between North
Logan and Union Street being one of the lengthier portions of the
meeting.
The city had heard in weeks prior that the Tremont Street project
was not going to be feasible for the Rebuild Illinois funds that had
originally been earmarked for the reconstruction of that road. The
timelines were not going to work out because the State Historic
Preservation Office would need to sign off on a portion of the
project. The time needed for that office to respond to a request was
going to exceed the deadline for when the Rebuild money would have
to be fully expended.
Aldermen reluctantly took the street off the 2024 construction
schedule, but also said they wanted to see another plan sooner
rather than later.
Tuesday evening the request for a new plan was
answered by Shane Remmert of Crawford Murphy and Tilly, the city’s
contracted engineers for road work.
The first plan presented was for the reconstruction of the street.
It is the most expensive plan, with the longest timeline to
completion. However, Remmert said that the life of the road would be
20 years or more, compared to the second plan with a life of only 10
years maximum.
In the reconstruction plan, preliminary engineering would cost
$183,100 and would begin in June of 2024 with an estimated
completion date of March 2025.
There would be letting out for bid after the design was approved and
finalized, then there would be an intent that the construction would
begin in May 2025 and would be completed in November 2026. The total
estimated cost of the construction would be $1,526,000. The
construction would run across two “seasons” or budget years and
would take up almost the entire budget for each year.
The second proposal was for a resurfacing project that would take
less time and cost less money, though it would still take the entire
budget for road construction in the budget year. The downside to the
less expensive plan is that it would not address all the needs of
the street and the work would have a life of only 10 years.
With plan two for resurfacing only the preliminary engineering
budget would be $84,000. Construction costs would come to an
estimated $763,000. The time timeline would be June through October
2024 for the design work and construction would be done between
April and October 2025.
It was also noted in the memo delivered to aldermen that the
estimated construction costs do not include the cost of utility
relocations or the construction engineering services.
[to top of second column] |
Remmert said he would ask if
there were any comments or questions from the aldermen. Alderman
Kevin Bateman was the first to speak offering his endorsement
for the more expensive plan. He said that he had been taught an
expression if you don’t have time to do it right the first time,
when will you have time to do it over again? He said 20 years or
more compared to ten years or less made it obvious to him that
the best plan would be to go for the 20-year plan.
Alderman Steve Parrott asked about the costs
increasing between now and 2025-2026? Remmert said, yes there is an
opportunity for costs to increase. He said that just like many
people look at the CPI (consumer price index) there is a CCI
(construction cost index) that does dictate that costs will go up
over time. He said the key point to make though was that delaying
decisions will mean stretching the timeline out even further, and
with each stretch, the potential for costs to increase will be
present.
He explained that one key component of holding the price will be in
the bid award. He said once the city goes out for bid on the project
and chooses the contractor, the contractor bid will be the dollar
amount held to throughout the construction in regard to known
materials and labor.
Alderwoman Wanda Lee Rohlfs said she was in agreement with Bateman
that the larger project was the right project to pursue. She asked
about the sidewalk and stair construction at the historic home on
the corner of Tremont and North Ottawa. Remmert said there was
engineering and surveying that would have to be done, as part of the
CMT design project. He said that for sake of the vote this coming
week, the question would be which program to support and
consequently the design work that would be included and conducted by
CMT.
It was noted that the reconstruction project would take two years to
complete and would take up almost all of the street and alley budget
for both of those two years. The exact costs will be determined as
the work progresses. Remmert said that he would come back to the
council with work orders that would have more precise numbers.
Mayor Tracy Welch said that for the sake of clarity,
the council should vote in the Monday March 3rd meeting on a motion
to approve the reconstruction plan. The request was made for the
item to be placed on the agenda.
The Monday agenda includes under new business (9B) “Approval of the
plan for reconstruction of Tremon Street from Union Street to Logan
Street in F.Y. 2024-2025 and F.Y. 2025-2026.”
As is always the case, aldermen have the right to table any voting
item if they feel they are not fully prepared to render an informed
decision.
It should be noted that Monday March 3rd will be the first meeting
where the council will meet at 6 p.m. instead of 7 p.m. Aldermen
voted in February to change the meeting time to 6 p.m. permanently
starting with the first meeting in March 2024.
[Nila Smith] |