Logan County Board Workshop Meeting
Logan County Courthouse Update
Send a link to a friend
[September 14, 2024]
On
the evening of September 12th, the Logan County Board met for their
monthly Workshop meeting, where they prepare for the following
week’s Regular Board meeting. Among other topics, an update was
given on the status of the courthouse restoration. This topic has
been brought up at many meetings, including both the Building and
Grounds and Finance committee meetings this month.
Board member Dale Nelson kicked off the courthouse update by giving
a rough estimate of the amounts of money the board has approved to
spend in relation to the cash flow they have available for the
project now. According to Nelson, the board has somewhere between
$1.1 to $1.2 million in cash flow. He also shared that the board
still has about $1 million left to pay on the CAD contract. He
further shared that the board approved five additional contracts in
relation to the courthouse restoration. The total of these contracts
is about $1.3 million. None of these contracts have been initiated
yet, so the board does not have to pay for any of them until they
are. Finally, Nelson stated that Bill Walter is currently helping
the county apply for a $2 million energy reimbursement rebate. Later
in the meeting, Walter was asked if this money is guaranteed, to
which Walter said that it was, it will just take some time to get.
Walter also gave an update on one of those five contracts, this one
being in relation to lights and the dome clocks at the courthouse.
He stated that the contractor’s bid may potentially fall through, at
which they would have to go looking for a bid from another
contractor. Walter was fairly confident that, as of the last time he
spoke with this contractor, he would still be able to complete the
work that he put the bid in for. Walter did say that he told this
contractor that, if by December 1st, he is not completely confident
that he will be able to perform the work, they will “pull the plug.”
The major issue with this is, if the board must go looking for a new
bid, it will very likely be higher than this previous contractor
agreed to work for. Walter said, “if I need to go back out, there’s
a possibility that the bid might come back twenty to forty percent
higher than what was originally submitted.”
Discussion over replacing windows in the courthouse
and the courthouse dome was also discussed. Walter stated that he
expects everything with the dome, including windows, to come in
somewhere in the range of $50,000-$75,000. Nelson asked when the
windows are going to be able to be installed, stating that he did
not believe windows could be installed once the temperature dropped
to a certain level or below. Walter assured Nelson and the board
that, with the material the contractors will be using to install the
windows, temperature will not be an issue. Walter added that they
are planning on getting more than one room done per day once the
windows do start getting replaced. The people that work in the
room(s) that are having the windows replaced are going to be asked
to relocate for one or two days, the amount of time it will take to
finish the installation.
[to top of second column] |
The board did ask Walter when he
anticipated the installation of the new windows was going to
begin. Walter shared that they are expecting the windows to
finish being manufactured by the second week of October. The
actual installation should take about two months once started.
An approximate date for the beginning of the installation
process was not given.
Next, board member Keenan Leesman asked for some clarification on
the board accepting bids when it did not have the money ready to do
so. It was stated that, while these bids were accepted, the board
had not started them yet, meaning they do not have to pay for
anything as of yet. The board could still decide not to go with a
certain contractor. It was also shared that, at any time, any of
these bids could change to go up. Walter tried to quell the board’s
fears that this would occur, stating that he keeps in touch with all
the contractors, and they all seem to be holding tight at the
original prices they bid at for now.
The final area of concern that was discussed was the
flat roof around the dome of the courthouse. There have been leaks
coming in through the roof, and one area where plywood is being used
in an attempt to keep the water out. While the issue was brought up
briefly toward the beginning of the meeting, when Sheriff Mark
Landers showed up later in the meeting, it was brought up again.
Landers stated that he was sent a picture of the roof the other day.
“There’s a lot of plywood, scrap, and garbage up there. I don’t know
why that hasn’t been cleaned up since [the contractors] are gone,”
said Landers. He continued saying the bell housing is where most of
the leaking is coming in. He has been telling his maintenance man
Trevor to not to replace the ceiling tiles because they are just
getting wet again, wasting money.
Board member Jim Wessbecher then brought up the fact that the roof
has been leaking for twenty-five years. His question was what has
been done in all that time to control the leak. Landers asked if the
flat roof is going to be fixed and if that is a part of the
restoration. Landers also made a suggestion regarding the bell,
since that is the major cause of leakage in the courthouse roof. He
suggested that the bell be taken down and replaced with a sound
system to mimic a bell. The original bell would then be put on
display outside the courthouse for everyone to see. Landers’s
questions and idea were listened to, but no one seemed to have any
answers or comments.
The September Regular Board meeting is going to take place next week
Tuesday at 6:00 p.m. on the first floor of the courthouse.
[Matt Boutcher] |