South Carolina's state utility says private firm set to restart 
		abandoned $9 billion nuclear project
		
		[October 25, 2025]  By 
		JEFFREY COLLINS 
						
		COLUMBIA, S.C. (AP)  South Carolina's state-owned utility is looking to 
		a private company to revive a project to build two nuclear power plants 
		that was abandoned eight years ago, losing more than $9 billion without 
		generating a watt of power. 
		 
		Santee Cooper's board agreed Friday to start six weeks of negotiations 
		with Brookfield Asset Management that they hope will lead to a deal that 
		lets the private company build the nuclear plants at the V.C. Summer 
		site near Jenkinsville at their own risk to generate power that they 
		could mostly sell to whom they want, such as energy-gobbling data 
		centers. 
		 
		Santee Cooper said Brookfield preliminarily agreed to provide the 
		utility with some of the power generated. But that and probably 
		thousands of other details will have to be negotiated. In a twist, 
		Brookfield took over the assets of Westinghouse Electric Co., which had 
		to declare bankruptcy because of difficulties building new nuclear 
		reactors. 
		 
		Utility officials said the agreement gives hope the state can get 
		something out of a debacle that led to four executives going to prison 
		or home confinement for lying to regulators, shareholders, ratepayers 
		and investigators and left millions of people paying for decades for a 
		project that never produced electricity. 
		 
		The risk to the ratepayer is nil. The risk to the taxpayer is nil, 
		Santee Cooper Board Chairman Peter McCoy said. 
		 
		There are still too many hurdles for the project to get past to consider 
		this a win right now, said Tom Clements, executive director of the 
		nuclear watchdog group Savannah River Site Watch. 
						
		
		  
						
		After eight years in the elements, all the equipment and the structure 
		of the plant, which was less than halfway finished, will need to be 
		carefully inspected before it can be used. The permits to build and the 
		licenses to operate the nuclear plants will need to be renewed, likely 
		starting from scratch, Clements said. 
		 
		I still believe that the cost, technical and regulatory hurdles are too 
		big to lead to completion of the project, Clements said, adding the 
		agreement appears to let Brookfield walk away if it decide it's not 
		feasible. 
		 
		
            [to top of second column]  | 
            
             
            
			  
            V.C. Summer Nuclear Station's unit two is shown under construction 
			near Jenkinsville, S.C., during a media tour of the facility 
			Wednesday, Sept. 21, 2016. (AP Photo/Chuck Burton) 
            
			  Santee Cooper heard from 70 bidders 
			and received 15 formal proposals to restart construction of the 
			reactors. Interest in the project has grown as power demand in the 
			U.S. surges with the increase in data centers as artificial 
			intelligence technology develops. 
			 
			Santee Cooper executives credited President Donald Trump's executive 
			order in May calling for the U.S. to quadruple the amount of power 
			generated by nuclear plants over the next 25 years for opening the 
			door to the potential agreement. 
			 
			You have placed South Carolina in the epicenter of the resurgence 
			of nuclear power in the United States, Santee Cooper CEO Jimmy 
			Staton said. 
			 
			Santee Cooper was the minority partner with what was then South 
			Carolina Electric and Gas when construction on the two new nuclear 
			plants started in 2013 at the V.C. Summer site  about 25 miles (40 
			kilometers) northeast of Columbia  where SCE&G was already 
			operating a reactor. 
			 
			The project needed to be finished in seven years to get tax credits 
			to keep the project's cost from overwhelming the utilities, but it 
			ended up behind schedule almost immediately. 
			 
			Executives lied about the problems to keep money coming in. 
			Taxpayers and ratepayers ended up on the hook because of a state law 
			that allowed the utilities to charge for costs before any power was 
			generated. 
			 
			Two nuclear reactors built in a similar way in Georgia went $17 
			billion over budget before they were fully operational in 2023. 
			
			
			All contents © copyright 2025 Associated Press. All rights reserved  |